Lake County, IL
File #: 16-0753    Version: 1 Name: Joint resolution executing a contract with Layne Christensen Company, Aurora, Illinois, in the amount not to exceed $224,949.00 for the 2016 Water Well Closure and Abandonment Project: Vernon Hills Wells 2 & 3 and Wildwood Wells 4 & 8 Project.
Type: resolution Status: Passed
File created: 7/28/2016 In control: Public Works and Transportation Committee
On agenda: Final action: 8/9/2016
Title: Joint resolution authorizing a contract with Layne Christensen Company of Aurora, Illinois, in an amount not to exceed $224,949 for the 2016 Water Well Closure and Abandonment Project: Vernon Hills wells two and three, and Wildwood wells four and eight.
Attachments: 1. 16-0753 Water Well Abandonment Bid Tab.pdf
Title
Joint resolution authorizing a contract with Layne Christensen Company of Aurora, Illinois, in an amount not to exceed $224,949 for the 2016 Water Well Closure and Abandonment Project: Vernon Hills wells two and three, and Wildwood wells four and eight.

Staff Summary
* The Vernon Hills and Wildwood water systems receive Lake Michigan Water from the Central Lake County Joint Action Water Agency (CLCJAWA).
* The Vernon Hills water system has interconnections with other municipalities as a backup water supply, while the Wildwood water system has additional wells as its backup water supply.
* An analysis was performed to determine the continued need for these wells and concluded that abandonment of these four wells is the most cost effective, long-term solution.
* An invitation to bid was extended to five contractors, 11 bidders registered for the bid, and responses were received from four contractors, ranging from $224,949 to $379,618.
* Layne Christensen Company of Aurora, Illinois, submitted the lowest responsive and responsible bid in the amount of $224,949.

Body
R E S O L U T I O N

WHEREAS, the County of Lake (County) owns, operates and maintains water systems throughout the County including water systems in Vernon Hills, and Wildwood; and

WHEREAS, the Vernon Hills and Wildwood water systems receive Lake Michigan Water from the Central Lake County Joint Action Water Agency, with backup emergency well systems remaining in place; and

WHEREAS, it was determined that the operation of Vernon Hills Wells two and three and Wildwood Wells four and eight should be discontinued and the wells be properly abandoned since other wells in the system or interconnections with other municipalities are used for back-up emergency use; and

WHEREAS, in accordance with the Lake County Purchasing Ordinance, bids were called for by publication for the 2016 Water Well Closure and Abandonment Project: Vernon Hills wells two and three, and Wildwood Wells four and eight...