File #: 21-0477    Version: 1 Name: Fairfield Road and Monaville Road: Consultant Change Order Number Two
Type: committee action item Status: Passed
File created: 3/17/2021 In control: Public Works, Planning & Transportation Committee
On agenda: Final action: 4/1/2021
Title: Joint committee action item approving Change Order Number Two consisting of an increase of $22,493.69 for additions to the Fairfield Road and Monaville Road intersection improvement Phase II consultant agreement.
Attachments: 1. 21-0477 Fairfield at Monaville Phase II CO#2, 2. 21-0477 Fairfiled at Monaville Committee Action Memo, 3. 21-0477 Location Map, Fairfield and Monaville Improvements, 4. 21-0477 Vendor Disclosure, Alfred Benesch

Title

Joint committee action item approving Change Order Number Two consisting of an increase of $22,493.69 for additions to the Fairfield Road and Monaville Road intersection improvement Phase II consultant agreement.

 

Staff Summary

                     Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.

                     The Fairfield Road and Monaville Road intersection improvement project is under contract with Alfred Benesch and Company, Chicago, Illinois, in the amount of $518,882.36 as approved by the County Board on April 10, 2018 and designated as Section 15-00120-06-CH. 

                     The sum of all contract change orders to date is $73,922.83, which represents a 14.25 percent increase over the original awarded contract amount.

 

Body

COMMITTEE ACTION ITEM

 

Summary:

 

Original awarded contract:                     $518,882.36

 

Change Order Number One:                     $51,429.14

Change Order Number Two:                     $22,493.69

Sum of all Change Orders:                     $73,922.83

 

Total revised contract amount (including all change orders): $592,805.19

 

Original contract appropriation amount:  $625,000