Title: Joint committee action item approving Change Order Number Two consisting of an increase of $22,493.69 for additions to the Fairfield Road and Monaville Road intersection improvement Phase II consultant agreement.
Attachments: 1. 21-0477 Fairfield at Monaville Phase II CO#2, 2. 21-0477 Fairfiled at Monaville Committee Action Memo, 3. 21-0477 Location Map, Fairfield and Monaville Improvements, 4. 21-0477 Vendor Disclosure, Alfred Benesch

Title

Joint committee action item approving Change Order Number Two consisting of an increase of $22,493.69 for additions to the Fairfield Road and Monaville Road intersection improvement Phase II consultant agreement.

 

Staff Summary

•                     Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.

•                     The Fairfield Road and Monaville Road intersection improvement project is under contract with Alfred Benesch and Company, Chicago, Illinois, in the amount of $518,882.36 as approved by the County Board on April 10, 2018 and designated as Section 15-00120-06-CH. 

•                     The sum of all contract change orders to date is $73,922.83, which represents a 14.25 percent increase over the original awarded contract amount.

 

Body

COMMITTEE ACTION ITEM

 

Summary:

 

Original awarded contract:                     $518,882.36

 

Change Order Number One:                     $51,429.14

Change Order Number Two:                     $22,493.69

Sum of all Change Orders:                     $73,922.83

 

Total revised contract amount (including all change orders): $592,805.19

 

Original contract appropriation amount:  $625,000