Legislation Details

File #: 11-0798    Version: 1 Name: Joint Committee Action approving Portwine Force Main Change Order #2 for Applied Technologies engineering services
Type: committee action item Status: Passed
File created: 7/27/2011 In control: Public Works and Transportation Committee
On agenda: Final action: 8/3/2011
Title: Joint committee action approving Change Order No. 2 for professional engineering services with Applied Technologies for design of the Portwine Lift Station Force Main Project.
Attachments: 1. 11-0798 Portwine LS Engineering Change Order 2.pdf

Title

Joint committee action approving Change Order No. 2 for professional engineering services with Applied Technologies for design of the Portwine Lift Station Force Main Project.

 

Staff Summary

•                     Change orders that exceed 10% of the original contract amount must be reviewed and approved by the PWT and F&A Committees.

•                     This change order associated with design work for the Portwine Lift Station Force Main Project totals $79,446 and exceeds 10% of the original contract.

•                     Change Order #1 in the amount of $40,764.65 was approved by the PWT and F&A Committees in March 2011.

•                     As part of the design phase of the project, Public Works staff worked with the Lake County Forest Preserve staff to secure an easement, which included determination of a tree impact fee estimated to be between $185,000 and $800,000.

•                     Public Works has secured an alternate route and easement for the force main in lieu of the Forest Preserve easement and tree impact fee, and anticipates a project cost saving of approximately $500,000.

•                     The alternate route will require re-design of a portion of the force main and necessitate additional engineering services in the amount of $79,446.

•                     Change Order #2 increases the amount of the engineering services contract by $79,446 from $207,752.65 to $287,198.65.