09-1408 13.1PWT Minutes of March 4, 2009minutesMinutes of March 4, 2009.approval of minutesPass Action details Not available
09-1351 17.1Alter Corporation Cost PresentationpresentationPresentation of the proposed Cornerstone Development -Alter Group.presented  Action details Not available
09-1432 17.2SWALCO Presentation on Countryside LandfillpresentationPresentation of an independent report assessing odor concerns at the Countryside Landfill.presented  Action details Not available
09-1414 17.3Executive Session for discussion of ongoing litigationpresentationExecutive Session for discussion of ongoing litigation.adopted  Action details Not available
09-1409 17.4Maintenance Facade Renovation MJG ContractresolutionJoint resolution awarding a contract to MJG Enterprises Corporation of Chicago, IL in the amount of $65,664 for the FY 2009 Maintenance Facility Facade Renovation Project.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1410 17.5PW Admin Bldg Window Replacement Rasch Constr ContractresolutionJoint resolution awarding a contract to Native Construction and Landscaping of Kansasville, WI in the amount of $73,800 for the FY 2009 Administration Building Window Replacement Project.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1411 17.6Wynstone North Barrington Sewage Disposal AgreementresolutionJoint resolution authorizing execution of an Agreement for Sewage Disposal Services for the area of the Wynstone Subdivision with the Village of North Barrington and the Village of Lake Zurich.presented  Action details Not available
09-1412 17.7PW Portwine Force Main Applied Technologies ContractresolutionJoint resolution authorizing execution of an agreement for professional engineering services with Applied Technologies for design of the Portwine Lift Station Parallel Force Main Project.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1413 17.8PW Plat of Vacation & Easement Grant for Sikora Subdivision MundeleinresolutionResolution authorizing the Director of Public Works to execute a Plat of Vacation and Easement Grant in Sikora’s Subdivision in the Village of Mundeleinapproved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1415 17.9Director's Report - Public Workscommunication or reportDirector’s Report - Public Workspresented  Action details Not available
09-1354 17.10Bid No. 90031 Sign Printer for DOTresolutionJoint resolution authorizing the Purchasing Agent to enter into a contract with the Sign Outlet Store, Lisle, IL for the purchase of a Roland Soljet Pro III Sign Shop Printer for the Division of Transportation in the amount of $31,516.80.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1377 17.11County Signals; New Traffic Signal Master Agreement: Village of LincolnshireresolutionJoint resolution authorizing the execution of a new master agreement between Lake County and the Village of Lincolnshire regarding the cost of maintenance, construction and installation, as well as future costs associated with current and future traffic control signals under the jurisdiction of the Lake County Division of Transportation and including provisions for emergency preemption systems.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1378 17.12Ice Control Salt (2009 – 2010 Winter Season): AppropriationresolutionJoint resolution appropriating $1,700,000 of Motor Fuel Tax funds for the supply of ice control salt materials needed for the 2009 - 2010 winter season and designated as Section 10-00000-00-GM.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1379 17.13Lake County PASSAGE, Wireless Communication Hub #2: Village of Wauconda AgreementresolutionJoint resolution authorizing the execution of a joint agreement between the Village of Wauconda and Lake County for the installation of Lake County PASSAGE wireless communication Hub #2 on a village owned water tower situated along Gilmer Road.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1380 17.14Lake County PASSAGE, City of Highland Park Signals: Consultant Agreement and Appropriation.resolutionJoint resolution authorizing a contract with Christopher B. Burke Engineering, Ltd., Rosemont, Illinois for professional services for Phase II design engineering services for 26 traffic signal modifications along various routes in the City of Highland Park including the Lake County PASSAGE interconnection at a maximum cost of $160,487.95 and appropriates $170,000 of Motor Fuel Tax funds and designated as Section 06-00924-00-TL.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1381 17.15Lake County PASSAGE, City of Highland Park Signals: IDOT Joint Agreement.resolutionJoint resolution authorizing an agreement between Lake County and the State of Illinois for the utilization of federal highway funds for Phase II design engineering services for 26 traffic signal modifications along various routes in the City of Highland Park including interconnection with Lake County PASSAGE and designated as Section 06-00924-00-TL.approved and referred on to Financial and Adminstrative Committee  Action details Not available
09-1382 17.16Fairfield Road at Bonner Road, Intersection Improvement: Contract AwardresolutionJoint resolution awarding a contract, for the improvement of the intersection of Fairfield Road at Bonner Road designated as Section 02-00113-15-CH, to Glenbrook Excavating & Concrete, Inc., Wauconda, Illinois in the amount of $1,125,050.48 for this improvement.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1383 17.17Fairfield Road at Nippersink Road Intersection Improvement, Right-of-way Acquisition: AppropriationresolutionJoint resolution appropriating $265,000 of Matching Tax funds for right-of-way costs associated with the proposed improvements to the intersection of Fairfield Road (County Highway 49) and Nippersink Road and designated as Section 02-00150-02-TL.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1389 17.18Peterson Road Widening and Reconstruction, US Rte. 45 to IL Rte. 83; Change Order No.1: Supplemental AppropriationresolutionJoint resolution appropriating a supplemental amount of $425,000 of Matching Tax funds for design engineering services for the Peterson Road improvement from US Rte. 45 to IL Rte. 83 and designated Section 07-00098-17-WR.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1390 17.19Peterson Road from US Rte. 45 to IL Rte. 83, Design Engineering Services: LCDOT Change Order No. 1committee action itemJoint committee action item approving Change Order No. 1 consisting of an increase of $399,636.76 for revisions to the design engineering services for the Peterson Road improvement from US Rte. 45 to IL Rte. 83 and designated as Section 07-00098-17-WR.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1391 17.20Midlothian Road Extension, from existing northerly terminus, northerly to Harris Road: Consultant Agreement and Appropriation.resolutionJoint resolution authorizing the execution of a contract with Spaceco, Inc. for Phase II design engineering services for the extension of Midlothian Road from its existing northerly terminus northerly to Harris Road at a maximum cost of services described of $157,143.31 and appropriates $50,000 of Matching Tax funds and $140,000 of the ¼ % Sales Tax for Transportation and Public Safety and designated as Section 09-00244-03-FP.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1401 17.21Western Avenue at Woodland Road; Intersection Improvements: City of Lake Forest Appropriation and AgreementresolutionJoint resolution authorizing the execution of an agreement with City of Lake Forest for the improvements to the intersection of Western Avenue and Woodland Road. This resolution appropriates $650,000 of the ¼% sales tax for Transportation and Public Safety for this improvement designated as Section 09-00931-00-CH.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1402 17.22Grass Lake Road Slope Wall Repairs at Grass Lake Road Bridge: AppropriationresolutionJoint resolution appropriating $125,000 of County Bridge Tax funds for the repairs to the Grass Lake Road bridge slope walls and designated as Section 09-00059-08-BR.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1403 17.23Prairie Crossing Bike Path along Midlothian Road (IL Rte 176 to Peterson Road; 3 Segments): Phase I Agreement and AppropriationresolutionJoint resolution authorizing the execution of a contract with McClure Engineering Associates Inc., Waukegan, Illinois for professional services for the provision of Phase I preliminary engineering services for three missing links in the Prairie Crossing Bike Path along Midlothian Road between IL Rte. 176 and Peterson Road at a maximum cost of services described of $73,787.97; and appropriates $90,000 of Matching Tax funds for this improvement and designated as Section 09-00171-13-BT.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1404 17.2421st Street and Russell Road Retaining Wall Phase II Engineering Services: Consultant Agreement and appropriationresolutionJoint resolution authorizing the execution of a contract with McClure Engineering Associates Inc., Waukegan, Illinois for professional services for the provision of Phase II engineering services for maintenance and repairs to retaining walls situated along 21st Street and Russell Road at a maximum cost of services described of $75,725.85; and appropriates $85,000 of Matching Tax funds and designated as Section 09-00999-08-GM.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1417 17.25Arlington Heights Road (Rt. 83 to Lake Cook Road), Resurfacing, and Buffalo Road Grove Road (Deerfield Parkway to IL Rte. 83) Resurfacing and Additional Southbound Lane: Construction AppropriationresolutionJoint resolution appropriating $3,070,000 of the ¼% Sales Tax for Transportation and Public Safety for joint repair and pavement grinding of Arlington Heights Road and Buffalo Grove Road and the addition of a through-lane on Buffalo Grove Road from IL Rte. 83 to Deerfield Road and designated as Section 08-00999-02-RP.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1418 17.26Winchester Road at IL Rte. 21; Intersection Improvement: AppropriationresolutionJoint resolution appropriating $679,000 of Motor Fuel Tax funds for the installation of a southbound to westbound right-turn lane on IL Rte. 21 at Winchester Road and extending the eastbound left-turn lane on Winchester Road and designated as Section 07-00151-19-CH.approved and referred on to the Financial and Administrative CommitteePass Action details Not available
09-1392 17.272009-2014 5-Years Highway Improvement Program: Schedule (Information)communication or report2009-2014 5-Year Highway Improvement Program: Schedulereceived and filedPass Action details Not available
09-1424 17.28Director's Report - Transportationcommunication or reportDirector’s Report - Transportationpresented  Action details Not available