Lake County, IL
File #: 11-1133    Version: 1 Name: Joint committee Approval CO 1 & 2 NCT WRF RHMG Engineering
Type: committee action item Status: Passed
File created: 10/24/2011 In control: Public Works and Transportation Committee
On agenda: Final action: 11/2/2011
Title: Joint committee action approving Change Order No. 2 for professional engineering services with RHMG, Inc. for design of the Vernon Hills NCT WRF Improvements Project.
Attachments: 1. 11-1133 NCT WRF Improvement RHMG Change Order #2.pdf
Title
Joint committee action approving Change Order No. 2 for professional engineering services with RHMG, Inc. for design of the Vernon Hills NCT WRF Improvements Project.
 
Staff Summary
·      Change orders that exceed 10% of the original contract amount must be reviewed and approved by the PWT and F&A Committees.
·      This change order associated with design work for the Vernon Hills NCT WRF improvements project totals $27,240 and exceeds 10% of the original contract.
·      As part of the design phase of the project, Public Works staff has increased the scope of the project by requesting additional operational and maintenance improvements be included in the design.
·      These additional improvements include replacement of the existing lighting in the Filter Building, replacement of the three overhead doors in the Filter Building, revision of the pump control system for the chlorine tank dewatering pumps, and inclusion of a new level control system for the clarifier pump station.
·      These additional items are necessary for proper operation and control of the plant. By including these items with this project, we will realize better cost efficiencies.
·      Change Order #2 increases the amount of the engineering services contract by $27,240 from $158,278 to $185,518.