Joint committee action approving Change Order No. 2 for professional engineering services with Applied Technologies for design of the Portwine Lift Station Force Main Project.
Staff Summary
• Change orders that exceed 10% of the original contract amount must be reviewed and approved by the PWT and F&A Committees.
• This change order associated with design work for the Portwine Lift Station Force Main Project totals $79,446 and exceeds 10% of the original contract.
• Change Order #1 in the amount of $40,764.65 was approved by the PWT and F&A Committees in March 2011.
• As part of the design phase of the project, Public Works staff worked with the Lake County Forest Preserve staff to secure an easement, which included determination of a tree impact fee estimated to be between $185,000 and $800,000.
• Public Works has secured an alternate route and easement for the force main in lieu of the Forest Preserve easement and tree impact fee, and anticipates a project cost saving of approximately $500,000.
• The alternate route will require re-design of a portion of the force main and necessitate additional engineering services in the amount of $79,446.