Lake County, IL
File #: 11-0525    Version: 1 Name: 2011 Bituminous Shoulder Maintenance Contract Award
Type: resolution Status: Passed
File created: 5/24/2011 In control: Public Works and Transportation Committee
On agenda: Final action: 6/14/2011
Title: Joint resolution awarding a contract for annual bituminous shoulder maintenance of sections of various county highways to the lowest responsible bidder Chicagoland Paving Contractors, Lake Zurich, Illinois, in the amount of $174,800 and designated as Section 11-00000-15-GM
Attachments: 1. 11-0525 2011 HMA Shoulder Bid Tabulation.pdf
Title
Joint resolution awarding a contract for annual bituminous shoulder maintenance of sections of various county highways to the lowest responsible bidder Chicagoland Paving Contractors, Lake Zurich, Illinois, in the amount of $174,800 and designated as Section 11-00000-15-GM

Staff Summary
· 2011 Bituminous Shoulder Maintenance: Contract Award.
· Each year the Division of Transportation contracts for bituminous shoulder maintenance throughout the county highway system.
· The added alternative bidding process was used for this letting.
· A total of five bids were received and the lowest responsible bidder is Chicagoland Paving Contractors, Lake Zurich, Illinois, in the amount of $174,800.

Body
R E S O L U T I O N

WHEREAS, pursuant to authority granted by this Lake County Board, the County Engineer heretofore called for sealed bids, by publication, for the bituminous shoulder maintenance comprised of sections of existing bituminous shoulder along the west side of Fairfield Road between Stub Avenue and IL Route 134 and sections of existing bituminous shoulder along the east side of Fairfield Road between IL Route 134 and Morningside Drive, and designated as Section 11-00000-15-GM; and

WHEREAS, in addition to the base bid work described above, the added alternative bidding process was used for bidders to provide costs for including Alternative A work, Alternative B work, and Alternative C work, with a total contract award limit of $200,000.

WHEREAS, added Alternative A work includes sections of existing bituminous shoulder along the east side of Fairfield Road between Morningside Drive and Lake Shore Drive; and

WHEREAS, added Alternative B work includes sections of existing bituminous shoulder along the east side of Fairfield Road between Lake Shore Drive and Rollins Road; and

WHEREAS, added Alternative C work includes sections of existing bituminous shoulder along Rollins Road between Mallard Creek and Nicole Lane; and

WHEREAS, pursuant to said pu...