Title
Joint committee action item approving Change Order No. 2 consisting of an increase of $79,737.50 for revisions to the design engineering services for the Peterson Road improvement from US Rte. 45 to West of IL Rte. 83 and designated as Section 07-00098-17-WR.
Staff Summary
· Peterson Road from US Rte. 45 to IL Rte. 83, Design Engineering Services: LCDOT Change Order No. 2
· Change orders need to be approved by the standing committees for cumulative net increases over 10%.
· The Peterson Road project is under contract for design originally totaling $541,066.39.
· Change Order 1 was the addition of the design of the intersection of IL 83 at Peterson Rd, formerly to be designed by the Village of Grayslake, into the County's project. ($399,636.76).
· A preliminary engineering phase was not utilized on this project since a corridor plat is on file; however, some items, normally handled in the preliminary engineering phase, now have to be addressed.
· This Change Order No. 2 is for the design engineering services work associated with centerline and plat of highway changes and the addition of corridor landscaping extending the project limits ($79,737.50).
Summary:
Original awarded contract $541,066.39 (Engineering Services)
Change Order No.1 $399,636.76
Change Order No.2 $79,737.50
Sum of all changes $1,020,440.65