File #: 11-0155    Version: 1 Name: Portwine LS FM Change Order #1 Applied Technologies
Type: committee action item Status: Passed
File created: 2/22/2011 In control: Public Works and Transportation Committee
On agenda: Final action: 3/2/2011
Title: Joint committee action Approving Change Order No. 1 for professional engineering services with Applied Technologies for design of the Portwine Lift Station Force Main Project.
Attachments: 1. 03.02.11 Portwine LS CO 1 Cost Summary Attachment.pdf
Title
Joint committee action Approving Change Order No. 1 for professional engineering services with Applied Technologies for design of the Portwine Lift Station Force Main Project.
Staff Summary
·      Change Orders that exceed 10% of the original contract amount must be reviewed and approved by the PWT and FA Committees.
·      This change order associated with design work for the Portwine Lift Station Force Main Project totals $40,764.65 and exceeds 10% of the original contract of $166,988.
·      Design changes leading to additional engineering services include:
o      Change from open cut method to directional boring construction to accommodate LCFPD easement requirements.
o      Attendance at additional design meetings between LCPWD and LCFPD staff.
o      Design changes necessary to accommodate actual conditions found in the NSSD carrier pipe.
o      Additional botanic, archaeological and wetlands surveys requested by LCFPD staff.
·      This Change Order increases the amount of the engineering services contract by $40,764.65 from $166,988 to $207,752.65.