Lake County, IL
File #: 22-0816    Version: 1 Name: Sheriff Community Based Corrections Center Roof Replacement
Type: resolution Status: Passed
File created: 5/26/2022 In control: Financial & Administrative Committee
On agenda: Final action: 6/14/2022
Title: Resolution authorizing execution of a contract with G.E. Riddiford Company, Inc., Arlington Heights, Illinois in the amount of $697,600 for the Sheriff Community Based Corrections Center (CBCC) Roof Replacement.
Attachments: 1. Vendor Disclosure Statement, 2. Bid 22061 Final, 3. 22061 Bid Tab
Title
Resolution authorizing execution of a contract with G.E. Riddiford Company, Inc., Arlington Heights, Illinois in the amount of $697,600 for the Sheriff Community Based Corrections Center (CBCC) Roof Replacement.

Staff Summary
* As part of the Fiscal Year 2022 Facility Assessment Budget and Facilities Capital Improvement Plan, Sheriff Community Based Corrections Center (CBCC) and Adult Detention Center Tower Roof Replacement was authorized.
* Following review of the bids submitted, Lake County determined to only award the roof replacement for the Sheriffs CBCC building.
* This work is a high priority project for Lake County. The existing building needs a full roof replacement as well as concrete crack repair, relocation of chiller coolant lines, installation of a new roof hatch and ladder for access to roof #2.
* The County received three bids for the project in the amount of $1,873,800 to $2,057,000.
* Award of this contract is recommended to the lowest responsive and responsible bidder, G.E. Riddiford Company, Inc., Arlington Heights, Illinois, who best meets the needs of the County in the amount of $697,600.
* This resolution authorizes and directs the County Purchasing Agent to execute a contract with G.E. Riddiford Company, Inc., Arlington Heights, Illinois, in the amount of $697,600.

Body
R E S O L U T I O N

WHEREAS, the County of Lake (County) owns, operates the Lake County Sheriffs Community Based Corrections Center (CBCC); and

WHEREAS, there is a need to replace the existing roof at the Sheriffs Office CBCC building; and

WHEREAS, this project includes full roof replacement as well as concrete crack repair, installation of a new roof hatch and ladder for access to roof #2, relocation of chiller coolant lines; and

WHEREAS, in accordance with the Lake County Purchasing Ordinance, bids were called for by publication for the Sheriff CBCC and Adult Detention Center Tower Roof Replacement; and

WHEREAS, G.E. Riddiford Company, Inc., is the lo...

Click here for full text