Title
Joint committee action item approving Change Order Number Four consisting of an increase of $16,828.32 for additions for the sidewalk and curb ramp improvements at the Quentin Road, at Illinois Route 22 intersection, contract.
Staff Summary
• Quentin Road, at Illinois Route 22, sidewalk and curb ramp improvements are under contract with Alliance Contractors, Inc., Woodstock, Illinois, in the amount of $233,808.41 as approved by the County Board on June 8, 2021, and designated as Section 20-00090-16-SW.
• Change Order Number Four consists of balancing quantities to final measurements and adjusting traffic signal equipment to fit the intent of the contract.
• Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• The sum of all contract change orders to date is $39,997.29, which represents a 17.11 percent increase over the original awarded contract amount.
Body
COMMITTEE ACTION ITEM
Summary:
Original awarded contract: $233,808.41
Change Order Number One: $2,934.96
Change Order Number Two: $3,000.02
Change Order Number Three: $17,233.99
Change Order Number Four: $16,828.32
Sum of all Change Orders: $39,997.29
Total revised contract amount (including all change orders): $273,805.70