Joint committee action item approving Change Order Number Two consisting of an increase of $143,098.56 for additions to the Illinois Route 137 Bike Path (Patriot Path) Phase I consultant agreement.
Staff Summary
• Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• The Illinois Route 137 Bike Path (Patriot Path) project is under contract with HR Green, Inc., McHenry, Illinois, in the amount of $1,360,893.69 as approved by the County Board on May 12, 2015 and designated as Section 15-00289-01-BT.
• The sum of all contract change orders to date is $271,991.58, which represents a 19.99 percent increase over the original awarded contract amount.
Body
COMMITTEE ACTION ITEM
Summary:
Original awarded contract: $1,360,893.69
Change Order Number One: $128,893.02
Change Order Number Two: $143,098.56
Sum of all Change Orders: $271,991.58
Total revised contract amount (including all change orders): $1,632,885.27.
Original contract appropriation amount: $1,635,000.