Title
Joint committee action item approving Change Order Number Two consisting of an increase of $296,595 for additions to the Quentin Road reconstruction Phase III construction engineering contract.
Staff Summary
• Phase III construction engineering for Quentin Road reconstruction is under contract with V3 Companies of Illinois, Woodridge, Illinois, in the amount of $2,334,894.88 as approved by the County Board on November 14, 2017, and designated as Section 08-00090-12-CH.
• Change Order Number Two is required due to contract completion extending an additional year because of delays caused by extensive utility conflicts and other unforeseen additional work.
• Change Order Number One was required as a partial balancing of final costs for the extended project duration.
• Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• The sum of all contract change orders to date is $529,851, which represents a 22.69 percent increase over the original awarded contract amount.
Body
COMMITTEE ACTION ITEM
Summary:
Original awarded contract: $2,334,894.88
Change Order Number One: $233,256
Change Order Number Two: $296,595
Sum of all Change Orders: $529,851
Total revised contract amount (including all change orders): $2,864,745.88.