Joint committee action item approving Change Order Number Two consisting of an increase of $22,493.69 for additions to the Fairfield Road and Monaville Road intersection improvement Phase II consultant agreement.
Staff Summary
• Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• The Fairfield Road and Monaville Road intersection improvement project is under contract with Alfred Benesch and Company, Chicago, Illinois, in the amount of $518,882.36 as approved by the County Board on April 10, 2018 and designated as Section 15-00120-06-CH.
• The sum of all contract change orders to date is $73,922.83, which represents a 14.25 percent increase over the original awarded contract amount.
Body
COMMITTEE ACTION ITEM
Summary:
Original awarded contract: $518,882.36
Change Order Number One: $51,429.14
Change Order Number Two: $22,493.69
Sum of all Change Orders: $73,922.83
Total revised contract amount (including all change orders): $592,805.19
Original contract appropriation amount: $625,000