File #: 20-0704    Version: 1 Name: IL Route 120, Knight Avenue to IL 131: Phase II Consultant Change Order Number 3
Type: committee action item Status: Passed
File created: 5/20/2020 In control: Public Works, Planning & Transportation Committee
On agenda: Final action: 6/4/2020
Title: Joint committee action item approving Change Order Number Three consisting of an increase of $21,883 to the Phase II engineering consultant agreement for the widening and resurfacing of Illinois Route 120, from Knight Avenue to Illinois Route 131.
Attachments: 1. 20-0704 IL Rte 120 Change Order 3 Supplement, 2. 20-0704 Location Map, IL Route 120 (Knight Ave to IL Route 131), 3. 20-0704 Vendor Disclosure, Patrick Engineering

Title

Joint committee action item approving Change Order Number Three consisting of an increase of $21,883 to the Phase II engineering consultant agreement for the widening and resurfacing of Illinois Route 120, from Knight Avenue to Illinois Route 131.

 

Staff Summary

                     Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.

                     Illinois Route 120 (Knight Avenue to Illinois Route 131) widening and resurfacing project is under contract with Patrick Engineering Inc., Lisle, Illinois, in the amount of $319,389.96 as approved by the County Board on November 11, 2015, and designated as Section 12-00999-31-WR.

                     Additional engineering services are necessary for several revisions to the original scope of work as detailed in the attached Supplement Number Three.

                     Change Order Number Three includes revisions to the plans required as a result of coordination with the Illinois Department of Transportation (IDOT) to accommodate their upcoming projects in the area as well as new IDOT permit plan requirements.

                     Change Order Number Two corrected an accounting error in the original contract document.

                     Change Order Number One included work to cover plan and plat revisions that resulted from ROW negotiations with adjacent property owner.

 

Body

COMMITTEE ACTION ITEM

 

Summary:

 

Original awarded contract:                     $ 319,389.96

 

Change Order Number One:                     $   23,865

Change Order Number Two:                     $     5,000

Change Order Number Three:                     $   21,883

Sum of all Change Orders:                     $   50,748

 

Total revised contract amount (including all change orders): $ 370,137.96

 

Original contract appropriation amount:  $ 385,000.