Lake County, IL
File #: 20-0556    Version: 1 Name: Wadsworth Road Safety Improvements and Resurfacing: Appropriation and Contract Award
Type: resolution Status: Passed
File created: 4/15/2020 In control: Public Works, Planning & Transportation Committee
On agenda: Final action: 5/12/2020
Title: Joint resolution authorizing a contract with Campanella and Sons, Inc., Wadsworth, Illinois, in the amount of $1,667,139.02 for the widening and resurfacing of Wadsworth Road, constructing a frontage road, and making repairs to a bridge over the Des Plaines River, and appropriating $2,000,000 of 1/4% Sales Tax for Transportation funds.
Attachments: 1. 20-0556 Bid Tab - Wadsworth Road Safety Improvement, 2. Vendor Disclosure, Campanella and Sons, 3. 20-0556 Wadsworth Road Safety Improvements Location Map.pdf

Title

Joint resolution authorizing a contract with Campanella and Sons, Inc., Wadsworth, Illinois, in the amount of $1,667,139.02 for the widening and resurfacing of Wadsworth Road, constructing a frontage road, and making repairs to a bridge over the Des Plaines River, and appropriating $2,000,000 of ¼% Sales Tax for Transportation funds.

 

Staff Summary

                     Wadsworth Road will be widened and resurfaced including construction of a frontage road, and making repairs to a bridge over the Des Plaines River.

                     There was a public call for bids, and two bids were received, ranging from $1,667,139.02 to $1,941,063.11, and the lowest responsible bidder is Campanella and Sons, Inc., in the amount of $1,667,139.02.

                     This project is included in the highway improvement program with construction in 2020, and designated as Section 19-00066-09-WR.

 

Body

R E S O L U T I O N

 

WHEREAS, pursuant to authority granted by this Lake County Board, the County Engineer heretofore called for sealed bids, by publication, for the widening and resurfacing of Wadsworth Road, constructing a frontage road, and making repairs to a bridge over the Des Plaines River; and

 

WHEREAS, pursuant to said publication and calling for said bids, sealed bids were received and opened on April 14, 2020, at 10:00 a.m. at the Lake County Division of Transportation in Libertyville, Illinois; a tabulation of said bids being as follows:

 

Campanella and Sons, Inc.

Wadsworth, Illinois

$1,667,139.02

 

Berger Excavating Contractors

Wauconda, Illinois

$1,941,063.11

 

WHEREAS, the Public Works, Planning and Transportation Committee, the County Engineer and the Purchasing Agent have examined each bid, and the lowest responsible bidder is Campanella and Sons, Inc., Wadsworth, Illinois, their bid being $1,667,139.02 based on estimated quantities and unit prices; and

 

WHEREAS, an appropriation of funds is required.

 

NOW, THEREFORE BE IT RESOLVED by this Lake County Board, that a contract be awarded to said Campanella and Sons, Inc., Wadsworth, Illinois, in accordance with their bid of $1,667,139.02, based on estimated quantities and unit prices, and that the Purchasing Agent, the County Clerk, and the County Engineer of Lake County be authorized and they are hereby directed to enter into a contract with said low bidder for the widening and resurfacing of Wadsworth Road, constructing a frontage road, and making repairs to a bridge over the Des Plaines River, and designated as Section 19-00066-09-WR.

 

BE IT FURTHER RESOLVED that in as much as such estimated quantities are the best approximation that can be determined at this time, these quantities may be added to, deducted from, or modified from in the final determination of the contract cost in accordance with Chapter 605 of the Illinois Compiled Statutes, Act 5, Section 5-205.2 without further Board action, providing the final cost chargeable to the funds appropriated does not exceed the appropriation.

 

BE IT FURTHER RESOLVED that there is hereby appropriated $2,000,000 of ¼% Sales Tax for Transportation funds.

 

DATED at Waukegan, Illinois, on May 12, 2020.