File #: 20-0384    Version: 1 Name: Rollins Road Drainage: Change Order Number Five
Type: committee action item Status: Passed
File created: 2/21/2020 In control: Public Works, Planning & Transportation Committee
On agenda: Final action: 3/5/2020
Title: Joint committee action item approving Change Order Number Five consisting of an increase of $6,412.44 for additions to the Rollins Road drainage construction contract.
Attachments: 1. 20-0384 Copenhaver Vendor Disclosure

Title

Joint committee action item approving Change Order Number Five consisting of an increase of $6,412.44 for additions to the Rollins Road drainage construction contract.

 

Staff Summary

                     Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.

                     Rollins Road drainage project is under contract with Copenhaver Construction Inc., Gilberts, Illinois, in the amount of $297,159.36 as approved by the County Board on August 8, 2017, and designated as Section 15-00080-60-DR. 

                     The contract included storm and sanitary removal and replacement; sodding (complete); erosion control; storm and sanitary structure removal, adjustment, and installation; trench backfill; hot-mix asphalt surface course; class D patches; and other related items.

                     Change Order Number Five consists of balancing earthwork and other minor items to final measured quantity.

                     Change Order Number Four was for additional work to fit to field conditions including a driveway replacement not originally anticipated, landscaping and sanitary manhole adjustment.

                     Change Order Number Three was for balancing quantities to field measurements and adding items for a sanitary manhole rebuild that was not anticipated, a boulder obstruction and repairing unmarked sanitary facilities that belong to the Lakes Regional Sanitary District.

                     Change Order Number Two was for underground traffic interconnect conduit relocation that was in conflict and some other minor field adjustments.

                     Change Order Number One was for adjustments to interconnect wire, additional tree removal that was not anticipated and other minor field adjustments.

                     Lakes Regional Sanitary District has already reimbursed per agreement for their facilities $51,612.21.

 

Body

COMMITTEE ACTION ITEM

 

Summary:

 

Original awarded contract:                     $297,159.36

 

Change Order Number One:                              -$1,434

Change Order Number Two:                        $10,100.90

Change Order Number Three:                          $5,718.29

Change Order Number Four:                        $15,128.09

Change Order Number Five:                          $6,412.44

Sum of all Change Orders:                        $35,925.72

 

Total revised contract amount (including all change orders): $333,085.08

 

Original contract appropriation amount:  $440,000