Title
Joint resolution ratifying an emergency procurement contract with Berger Excavating Contractors, Inc., Wauconda, Illinois, in the amount of $162,029 for contractual construction services required to replace a failing corrugated metal storm sewer pipe under Grass Lake Road, 350 feet west of Sibley Drive in Antioch, Illinois, and appropriating a supplemental amount of $3,000 of County Bridge Tax funds.
Staff Summary
* On September 19, 2019, the County Engineer declared an emergency to replace a failing corrugated metal storm sewer pipe under Grass Lake Road, 350 feet west of Sibley Drive in Antioch, Illinois?
* In accordance with Article 6-103 of the Lake County Purchasing Ordinance, the County Engineer certified an emergency procurement for contractual construction services.
* The contractor selected to provide emergency contractual construction services is Berger Excavating Contractors, Inc. in the amount of $162,029 and designated as Section 17-00059-12-ES.
* This Lake County Board, on October 8, 2019 approved an appropriation of $160,000 of County Bridge Tax funds and awarded Berger Excavating Contractors, Inc. a contract in the amount of $128,234.
Body
R E S O L U T I O N
WHEREAS, Grass Lake Road, County Highway 18, is a designated route on the County highway system; and
WHEREAS, the corrugated metal storm sewer pipe under Grass Lake Road, 350 feet west of Sibley Drive in Antioch, Illinois, is failing causing a safety hazard for the traveling public; and
WHEREAS, on September 19, 2019, in accordance with Article 6-103 of the Lake County Purchasing Ordinance, the County Engineer of Lake County declared that an emergency existed and certified an emergency procurement; and
WHEREAS, a contract, in the amount of $162,029, has been awarded to Berger Excavating Contractors, Inc., Wauconda, Illinois, a qualified construction firm having the necessary manpower, equipment, materials and expertise to implement the determined repairs to the corrugated me...