File #: 19-0764    Version: 1 Name: 2019 Grant Road District: Contract Award
Type: resolution Status: Passed
File created: 4/25/2019 In control: Public Works, Planning & Transportation Committee
On agenda: Final action: 5/14/2019
Title: Joint resolution authorizing a contract with Peter Baker and Son Company, Lake Bluff, Illinois, in the amount of $431,448.54 for Hot-Mix Asphalt Surface Removal, patching and construction of Surface Course and Leveling Binder on various roads in the Grant Township Road District, which will be improved under the Illinois Highway Code for a total of 2.4 miles.
Attachments: 1. 19-0764 Bid Tab, 2019 Grant Road District

Title

Joint resolution authorizing a contract with Peter Baker and Son Company, Lake Bluff, Illinois, in the amount of $431,448.54 for Hot-Mix Asphalt Surface Removal, patching and construction of Surface Course and Leveling Binder on various roads in the Grant Township Road District, which will be improved under the Illinois Highway Code for a total of 2.4 miles.

 

Staff Summary

                     There was a public call for bids, and a total of three bids were received, ranging from $431,448.54 to $545,220.36, and the lowest responsible bidder is Peter Baker and Son Company, Lake Bluff, Illinois, in the amount of $431,448.54.

                     This improvement is designated as Section 19-08183-01-GM.

 

Body

R E S O L U T I O N

 

WHEREAS, pursuant to authority granted by this Lake County Board and the Grant Township Road District Highway Commissioner, the County Engineer heretofore called for sealed bids, by publication, for the Hot-Mix Asphalt Surface Removal, patching and construction of Surface Course and Leveling Binder on various roads in the Grant Township Road District, and designated as Section 19-08183-01-GM.

 

WHEREAS, pursuant to said publication calling for said bid, sealed bids were received and opened on April 16, 2019, at 10:00 a.m. at the Lake County Division of Transportation in Libertyville, Illinois; a tabulation of said bids being as follows:

 

Peter Baker and Son Company

Lake Bluff, Illinois

$431,448.54

 

J.A. Johnson Paving Company

Arlington Heights, Illinois

$478,974.12

 

Payne and Dolan, Inc.

Antioch, Illinois

$545,220.36

 

WHEREAS, the Public Works, Planning and Transportation Committee, the County Engineer and the Purchasing Agent have examined each bid, and it appears that the lowest responsible bidder is Peter Baker and Son Company, Lake Bluff, Illinois, their bid being $431,448.54 based on estimated quantities and unit prices; and

 

NOW, THEREFORE BE IT RESOLVED by this Lake County Board, that a contract be awarded to said Peter Baker and Son Company, Lake Bluff, Illinois, in accordance with their bid of $431,448.54, based on estimated quantities and unit prices, and that the Purchasing Agent, the County Clerk, and the County Engineer of Lake County be authorized and they are hereby directed to enter into a contract with said low bidder for the Hot-Mix Asphalt Surface Removal, patching and construction of Binder Course and Leveling Binder on various roads in the Grant Township Road District, which will be improved under the Illinois Highway Code for a total of 2.4 miles, and designated as Section 19-08183-01-GM.

 

BE IT FURTHER RESOLVED that in as much as such estimated quantities are the best approximation that can be determined at this time, these quantities may be added to, deducted from, or modified from in the final determination of the contract cost in accordance with Chapter 605 of the Illinois Compiled Statutes, Act 5, Section 5-205.2 without further Board action.

 

BE IT FURTHER RESOLVED that this award be processed by the County Engineer for final approval of the Illinois Department of Transportation in accordance with the “Agreement of Understanding” between the Illinois Department of Transportation and Lake County, dated May 3, 2018, and subject to the approval of the Grant Township Road District Commissioner.

 

DATED at Waukegan, Illinois, on May 14, 2019.