Lake County, IL
File #: 19-0498    Version: 1 Name: 2019 Cuba Township Road District: Contract Award
Type: resolution Status: Passed
File created: 3/20/2019 In control: Public Works, Planning & Transportation Committee
On agenda: Final action: 4/9/2019
Title: Joint resolution authorizing a contract with Peter Baker and Son Company, Lake Bluff, Illinois, in the amount of $277,807.06 for the construction of leveling binder and surface course lifts on an existing milled surface on various roads in the Cuba Township Road District, which will be improved under the Illinois Highway Code for a total of 1.3 miles.
Attachments: 1. 19-0498 Bid Tab, Cuba Road District 2019

Title

Joint resolution authorizing a contract with Peter Baker and Son Company, Lake Bluff, Illinois, in the amount of $277,807.06 for the construction of leveling binder and surface course lifts on an existing milled surface on various roads in the Cuba Township Road District, which will be improved under the Illinois Highway Code for a total of 1.3 miles.

 

Staff Summary

                     There was a public call for bids, and a total of four bids were received, ranging from $277,807.06 to $372,700, and the lowest responsible bidder is Peter Baker and Son Company in the amount of $277,807.06.

                     This improvement is designated as Section 19-04000-00-GM.

 

Body

RESOLUTION

 

WHEREAS, pursuant to authority granted by this Lake County Board and the Cuba Township Road District Highway Commissioner, the County Engineer heretofore called for sealed bids, by publication, for the construction of leveling binder and surface course lifts on an existing milled surface on various roads in the Cuba Township Road District, and designated as Section 19-04000-00-GM; and

 

WHEREAS, pursuant to said publication and calling for said bids, sealed bids were received and opened on March 12, 2019, at 10:00 a.m. at the Lake County Division of Transportation in Libertyville, Illinois, a tabulation of said bids being as follows:

 

Peter Baker and Son Company

Lake Bluff, Illinois

$277,807.06

 

Arrow Road Construction Company

Mount Prospect, Illinois

$331,965.96

 

Builders Paving, LLC

Hillside, Illinois

$357,500

 

J.A. Johnson Paving Company

Arlington Heights, Illinois

$372,700

 

WHEREAS, the Public Works, Planning and Transportation Committee, the County Engineer and the Purchasing Agent have examined each bid, and it appears that the lowest responsible bidder is Peter Baker and Son Company their bid being $277,807.06, based on estimated quantities and unit prices.

 

NOW, THEREFORE BE IT RESOLVED by this Lake County Board, that a contract be awarded to said Peter Baker and Son Company, Lake Bluff, Illinois, in accordance with their bid of $277,807.06, based on estimated quantities and unit prices, and that the Purchasing Agent, the County Clerk, and the County Engineer of Lake County be authorized and they are hereby directed to enter into a contract with said low bidder for  construction of leveling binder and surface course lifts on an existing milled surface on various roads in the Cuba Township Road District, which will be improved under the Illinois Highway Code for a total of 1.3 miles, and designated as Section 19-04000-00-GM.

 

BE IT FURTHER RESOLVED that in as much as such estimated quantities are the best approximation that can be determined at this time, these quantities may be added to, deducted from, or modified from in the final determination of the contract cost in accordance with Chapter 605 of the Illinois Compiled Statutes, Act 5, Section 5-205.2 and Section 6-701.1 without further Board action.

 

BE IT FURTHER RESOLVED that this award be processed by the County Engineer for final approval of the Illinois Department of Transportation in accordance with the “Agreement of Understanding” between the Illinois Department of Transportation and Lake County, dated May 3, 2018, and subject to the approval of the Cuba Township Road District Highway Commissioner.

 

DATED at Waukegan, Illinois, on April 9, 2019.