Lake County, IL
File #: 18-1377    Version: 1 Name: Joint committee action approving Change Order #3 for the Mill Creek WRF Clarifier Work Project contract changes with Fab Tech Wastewater Solutions, LLC of O’Fallon, MO in the amount of $37,375.
Type: committee action item Status: Passed
File created: 10/30/2018 In control: Public Works and Transportation Committee
On agenda: Final action: 11/7/2018
Title: Joint committee action approving Change Order Number Three for the Mill Creek Water Reclamation Facility (WRF) clarifier work project contract changes with Fab Tech Wastewater Solutions, LLC, O'Fallon, Missouri, in the amount of $37,375.
Attachments: 1. 18-1377 Mill Creek WRF Clarifier Change Order 3 Site Map-Exhibit A.pdf, 2. 18-1377 Mill Creek WRF Clarifier Change Order 3 Clarifier Photo-Exhibit B.pdf

Title

Joint committee action approving Change Order Number Three for the Mill Creek Water Reclamation Facility (WRF) clarifier work project contract changes with Fab Tech Wastewater Solutions, LLC, O’Fallon, Missouri, in the amount of $37,375.

 

Staff Summary

                     On May 7, 2018 a purchase order for $225,000 was issued to Fab Tech Waste Water Solutions, LLC for rehabilitation to extend the service life of the clarifiers.

                     Two change orders were issued to address unforeseen conditions in clarifier number one. The work included fabricating  a new stainless steel suction header, flushing device and cage repairs.

                     Change Order Number Three replaces the influent wells for both clarifiers and fabricates a stainless-steel suction header and repairs the cage of clarifier number two.  This equipment was originally intended to be rehabilitated with sand blasting and recoating but the amount of corrosion was found to be extensive, requiring the components to be replaced.

                     In accordance with Article 8, section 101(2) of the Lake County Purchasing Ordinance, these change orders were not reasonably foreseeable at the time the contract was signed.

                     Change Order Three is in the amount of $37,375 increasing the previous contract amount from $242,775 to $280,150.

 

Body

 

CHANGE ORDER

 

Original awarded contract:

$ 225,000

 

 

Change Order One:

$  13,975

Change Order Two:

$    3,800

Change Order Three:

$  37,375

Sum of all changes:

$  55,150

 

 

Total amount, including change orders

$280,150