Lake County, IL
File #: 18-0751    Version: 1 Name: Kelsey Road Resurfacing: Appropriation and Contract Award
Type: resolution Status: Passed
File created: 6/20/2018 In control: Public Works and Transportation Committee
On agenda: Final action: 7/10/2018
Title: Joint resolution authorizing a contract with Peter Baker and Son Company, Lake Bluff, Illinois, (Peter Baker and Son) in the amount of $1,932,980.80 for the resurfacing of Kelsey Road, from Illinois Route 22 to Illinois Route 59, which will be improved under the Illinois Highway Code for a total of 3.7 miles, appropriating $2,320,000 of Motor Fuel Tax funds, and designated as Section 17-00068-08-RS.
Attachments: 1. 18-0751 Bid Tab, Kelsey Road Resurfacing.pdf

Title

Joint resolution authorizing a contract with Peter Baker and Son Company, Lake Bluff, Illinois, (Peter Baker and Son) in the amount of $1,932,980.80 for the resurfacing of Kelsey Road, from Illinois Route 22 to Illinois Route 59, which will be improved under the Illinois Highway Code for a total of 3.7 miles, appropriating $2,320,000 of Motor Fuel Tax funds, and designated as Section 17-00068-08-RS.

 

Staff Summary

                     Kelsey Road, from Illinois Route 22 to Illinois Route 59, needs resurfacing.

                     This resurfacing improvement has been identified within the County’s pavement management system and is included in the highway improvement program.

                     A total of three bids were received, ranging from $1,932,980.80 to $2,612,346.45, and the lowest responsible bidder is Peter Baker and Son with a contract amount of $1,932,980.80.

 

Body

R E S O L U T I O N

 

WHEREAS, pursuant to authority granted by this Lake County Board, the County Engineer heretofore called for sealed bids, by publication, for the resurfacing of Kelsey Road, from Illinois Route 22 to Illinois Route 59, which will be improved under the Illinois Highway Code for a total of 3.7 miles; and

 

WHEREAS, pursuant to said publication and calling for said bids, sealed bids were received and opened on June 19, 2018, at 10:00 a.m. at the Lake County Division of Transportation in Libertyville, Illinois, a tabulation of said bids being as follows:

 

Peter Baker and Son Company

Lake Bluff, Illinois

$1,932,980.80

 

Builders Paving, LLC

Hillside, Illinois

$2,368,000

 

Lorig Construction Company

Des Plaines, Illinois

$2,612,346.45

 

WHEREAS, the Public Works and Transportation Committee, the County Engineer and the Purchasing Agent have examined each bid, and it appears that the lowest responsible bidder is Peter Baker and Son Company, Lake Bluff, Illinois, their bid being $1,932,980.80 based on estimated quantities and unit prices; and

 

WHEREAS, an appropriation of funds is required.

 

NOW, THEREFORE BE IT RESOLVED by this Lake County Board, that a contract be awarded to said Peter Baker and Son Company, Lake Bluff, Illinois, in accordance with their bid of $1,932,980.80 based on estimated quantities and unit prices and that the Purchasing Agent, the County Clerk, and the County Engineer of Lake County be authorized and they are hereby directed to enter into a contract with said low bidder for the resurfacing of Kelsey Road, from Illinois Route 22 to Illinois Route 59, which will be improved under the Illinois Highway Code for a total of 3.7 miles, and designated as Section 17-00068-08-RS.

 

BE IT FURTHER RESOLVED, that in as much as such estimated quantities are the best approximation that can be determined at this time, these quantities may be added to, deducted from, or modified from in the final determination of the contract cost in accordance with Chapter 605 of the Illinois Compiled Statutes, Act 5, Section 5-205.2 without further Board action, providing the final cost chargeable to the funds appropriated does not exceed the appropriations provided.

 

BE IT FURTHER RESOLVED, that the Clerk is hereby directed to transmit four certified originals of this resolution to the district office of the Department of Transportation.

 

BE IT FURTHER RESOLVED that there is hereby appropriated $2,320,000 of Motor Fuel Tax funds.

 

BE IT FURTHER RESOLVED, that this award be processed by the County Engineer for final approval of the Illinois Department of Transportation in accordance with the “Agreement of Understanding” between the Illinois Department of Transportation and Lake County, dated May 3, 2018.

 

DATED at Waukegan, Illinois, on July 10, 2018.