Title
Joint committee action approving Change Order Number One for Public Works Painting Projects with BP&T Company, Mount Prospect, Illinois, in the amount of $6,175.
Staff Summary
• A contract was awarded to BP&T Company for painting lift stations as part of Public Works Painting Projects in November 2017.
• Change Order Number One addresses additional painting work needed at two lift stations that was unforeseen at the time when the project bids were prepared.
• In accordance with Article 8, section 101(2) of the Lake County Purchasing Ordinance, this change order was not reasonably foreseeable at the time the contract was signed.
• Change Order Number One is in the amount of $6,175, increasing the original contract amount from $25,800 to $31,975.
Body
Change Order Request
Original awarded contract: $25,800
Change Order One: $ 6,175
Sum of all changes: $31,975