File #: 18-0625    Version: 1 Name: Joint committee action approving Change Order #1 for the Public Works Painting Projects with BP&T Co., Mt. Prospect, IL in the amount of $6,175.
Type: committee action item Status: Passed
File created: 5/30/2018 In control: Public Works and Transportation Committee
On agenda: Final action: 6/6/2018
Title: Joint committee action approving Change Order Number One for Public Works Painting Projects with BP&T Company, Mount Prospect, Illinois, in the amount of $6,175.

Title

Joint committee action approving Change Order Number One for Public Works Painting Projects with BP&T Company, Mount Prospect, Illinois, in the amount of $6,175.

 

Staff Summary

                     A contract was awarded to BP&T Company for painting lift stations as part of Public Works Painting Projects in November 2017. 

                     Change Order Number One addresses additional painting work needed at two lift stations that was unforeseen at the time when the project bids were prepared.

                     In accordance with Article 8, section 101(2) of the Lake County Purchasing Ordinance, this change order was not reasonably foreseeable at the time the contract was signed.

                     Change Order Number One is in the amount of $6,175, increasing the original contract amount from $25,800 to $31,975.

 

Body

Change Order Request

 

Original awarded contract:                                          $25,800

 

Change Order One:                                                               $ 6,175

 

Sum of all changes:                                          $31,975