File #: 18-0509    Version: 1 Name: Joint committee action approving Change Order Number One for the Vernon Hills Water System electrical and mechanical upgrade project design scope revisions with Donohue & Associates, Inc., Sheboygan, Wisconsin, in the amount of $34,515.
Type: committee action item Status: Passed
File created: 4/25/2018 In control: Public Works and Transportation Committee
On agenda: Final action: 5/2/2018
Title: Joint committee action approving Change Order Number One for the Vernon Hills Water System Electrical and Mechanical Upgrade Project design scope revisions with Donohue and Associates, Inc., Sheboygan, Wisconsin, in the amount of $34,515.

Title

Joint committee action approving Change Order Number One for the Vernon Hills Water System Electrical and Mechanical Upgrade Project design scope revisions with Donohue and Associates, Inc., Sheboygan, Wisconsin, in the amount of $34,515.

 

Staff Summary

                     On July 28, 2017 a purchase order was issued to Donohue and Associates, Inc. for the preparation of design and bidding documents for Vernon Hills Water System Electrical and Mechanical Upgrade Project.

                     Change Order Number One addresses unforeseen increases in the scope of the design work at the eight individual sites that comprise the project.

                     In accordance with Article 8, section 101(2) of the Lake County Purchasing Ordinance, this change order was not reasonably foreseeable at the time the contract was signed.

                     Change Order Number One is in the amount of $34,515 increasing the previous contract amount from $130,750 to $165,265.

 

body

 

CHANGE ORDER

 

Original Contract Award

$130,750

 

 

Change Order Number One

$34,515

Total sum of Change orders:

$34,515

 

 

Total cost

$165,265