Lake County, IL
File #: 18-0495    Version: 1 Name: 2018 Wauconda Road District: Contract Award
Type: resolution Status: Passed
File created: 4/23/2018 In control: Public Works and Transportation Committee
On agenda: Final action: 5/8/2018
Title: Joint resolution authorizing a contract with Peter Baker and Son Company, Lake Bluff, Illinois, in the amount of $52,817.44 for the resurfacing of Dowell Road, from the McHenry County Line to the Neville Road intersection and from the Darrell Road intersection to the Village of Island Lake limits in Wauconda Township Road District, which will be improved under the Illinois Highway Code for a total of 0.27 miles, and designated as Section 18-15000-00-GM.
Attachments: 1. 18-0495 Bid Tab, Wauconda Road District.pdf

Title

Joint resolution authorizing a contract with Peter Baker and Son Company, Lake Bluff, Illinois, in the amount of $52,817.44 for the resurfacing of Dowell Road, from the McHenry County Line to the Neville Road intersection and from the Darrell Road intersection to the Village of Island Lake limits in Wauconda Township Road District, which will be improved under the Illinois Highway Code for a total of 0.27 miles, and designated as Section 18-15000-00-GM.

 

Staff Summary

                     The Division of Transportation manages the engineering of the Township road district projects funded with Motor Fuel Tax. 

                     This resurfacing is for Dowell Road, from the McHenry County line to the Neville Road intersection, and from the Darrell Road intersection to the Village of Island Lake limits in Wauconda Township Road District.

                     A total of four bids were received, ranging from $52,817.44 to $68,983.82, and the lowest responsible bidder is Peter Baker and Son Company, Lake Bluff, Illinois, in the amount of $52,817.44.

 

Body

R E S O L U T I O N

 

WHEREAS, pursuant to authority granted by this Lake County Board and the Wauconda Township Road District Highway Commissioner, the County Engineer heretofore called for sealed bids, by publication, for the resurfacing of Dowell Road, from the McHenry County Line to the Neville Road intersection and from the Darrell Road intersection to the Village of Island Lake limits in Wauconda Township Road District, and designated as Section 18-15000-00-GM; and

 

WHEREAS, pursuant to said publication and calling for said bids, sealed bids were received and opened on April 17, 2018, at 10:00 A.M. at the Lake County Division of Transportation in Libertyville, Illinois, a tabulation of said bids being as follows:

 

Peter Baker and Son Company

Lake Bluff, Illinois

$52,817.44

 

Chicagoland Paving, Inc.

Lake Zurich, Illinois

$58,900

 

Lorig Construction Company

Des Plaines, Illinois

$68,061.04

 

Geske and Sons, Inc.

Crystal Lake, Illinois

$68,983.82

 

WHEREAS, the Public Works and Transportation Committee, the County Engineer and the Purchasing Agent have examined each bid, and it appears that the lowest responsible bidder is Peter Baker and Son Company, Lake Bluff, Illinois, their bid being $52,817.44, based on estimated quantities and unit prices.

 

NOW, THEREFORE BE IT RESOLVED by this Lake County Board, that a contract be awarded to said Peter Baker and Son Company, Lake Bluff, Illinois, in accordance with their bid of $52,817.44, based on estimated quantities and unit prices, and that the Purchasing Agent, the County Clerk, and the County Engineer of Lake County be authorized and they are hereby directed to enter into a contract with said low bidder for  the resurfacing of Dowell Road, from the McHenry County Line to the Neville Road intersection and from the Darrell Road intersection to the Village of Island Lake limits in Wauconda Township Road District, which will be improved under the Illinois Highway Code for a total of 0.27 miles, and designated as Section 18-15000-00-GM.

 

BE IT FURTHER RESOLVED that in as much as such estimated quantities are the best approximation that can be determined at this time, these quantities may be added to, deducted from, or modified from in the final determination of the contract cost in accordance with Chapter 605 of the Illinois Compiled Statutes, Act 5, Section 5-205.2 and Section 6-701.1 without further Board action.

 

BE IT FURTHER RESOLVED that this award be processed by the County Engineer for final approval of the Illinois Department of Transportation in accordance with the “Agreement of Understanding” between the Illinois Department of Transportation and Lake County, dated January 18, 2013, and subject to the approval of the Wauconda Township Road District Highway Commissioner.

 

DATED at Waukegan, Illinois, on May 8, 2018.