Joint resolution authorizing a contract with Construction Cleaning Company, Chicago, Illinois (Construction Cleaning) and further authorizing assignment of that contract to Clark Construction Group LLC, Chicago, Illinois, (Clark) as Construction Manager at Risk (CMAR) for the final cleaning work for the Lake County Courthouse Expansion Project (LCCEP) in the amount of $109,400.
Staff Summary
* The final cleaning work in this bid generally includes all interior and exterior final construction cleaning for the LCCEP.
* The Lake County Board has authorized Clark to proceed with a Guaranteed Maximum Price (GMP) for the infrastructure and interior work pursuant to their contract for CMAR services.
* A bid was issued for final cleaning work on February 2, 2018.
* Sealed bids were received on March 1, 2018, from three nonlocal vendors ranging from $109,400 to $390,000.
* Construction Cleaning was determined to be the lowest responsive and responsible bidder.
Body
RESOLUTION
WHEREAS, in accordance with Section 5-102 of the Lake County Purchasing Ordinance, a bid was called for by publication for Final Cleaning work for LCCEP; and
WHEREAS, sealed bids were received from three vendors at the Lake County Administrative Building, Waukegan, Illinois, on March 1, 2018, at 2:00 p.m.; and
WHEREAS, based on the criteria set forth in the Bid; the staff evaluated the bid submitted and determined that the bid submitted by Construction Cleaning Company, Chicago, Illinois in the amount of $109,400 is the lowest responsive and responsible bidder for Lake County; and
WHEREAS, On April 9, 2013, the Lake County Board authorized a contract for Construction Manager at Risk Services with a Guaranteed Maximum Price (GMP) for the LCCEP with Clark Construction Group LLC of Chicago, Illinois; and
WHEREAS, On June 9, 2015, the Lake County Board authorized Clark Construction to proceed with the GMP for the construction of the LCCEP work described as the Infrastructure and Interio...
Click here for full text