Lake County, IL
File #: 17-0372    Version: 1 Name: 2017 Warren Township Road District: Contract Award
Type: resolution Status: Passed
File created: 3/28/2017 In control: Public Works and Transportation Committee
On agenda: Final action: 4/11/2017
Title: Joint resolution authorizing a contract with Peter Baker & Son Company, Lake Bluff, Illinois, in the amount of $21,415.06 for the Hot-Mix Asphalt (HMA) surface removal, patching and the addition of HMA leveling binder and surface courses on Magnolia Avenue in the Warren Township Road District, and designated as Section 17-14149-01-GM.
Attachments: 1. 17-0372 Bid Tab, Warren Road District 2017.pdf

Title

Joint resolution authorizing a contract with Peter Baker & Son Company, Lake Bluff, Illinois, in the amount of $21,415.06 for the Hot-Mix Asphalt (HMA) surface removal, patching and the addition of HMA leveling binder and surface courses on Magnolia Avenue in the Warren Township Road District, and designated as Section 17-14149-01-GM.

 

Staff Summary

                     2017 Warren Township Road District: Contract Award.

                     A total of four bids were received ranging from $21,415.06 to $35,918.06 with Peter Baker & Son Company, Lake Bluff, Illinois, being the lowest responsible bidder with a contract amount of $21,415.06.

                     This project is included in the highway improvement program.

 

Body

R E S O L U T I O N

 

WHEREAS, pursuant to authority granted by this Lake County Board and the Warren Township Road District Highway Commissioner, the County Engineer heretofore called for sealed bids, by publication, for the Hot-Mix Asphalt (HMA) surface removal, patching and the addition of HMA leveling binder and surface courses on Magnolia Avenue in the Warren Township Road District, and designated as Section 17-14149-01-GM; and

 

WHEREAS, pursuant to said publication and calling for said bids, sealed bids were received and opened on March 21, 2017, at 10:00 A.M. at the Lake County Division of Transportation in Libertyville, Illinois, a tabulation of said bids being as follows:

 

Peter Baker & Son Company

Lake Bluff, Illinois

$21,415.06

 

Schroeder Asphalt Services, Inc.

Huntley, Illinois

$25,295.06

 

Chicagoland Paving, Inc.

Lake Zurich, Illinois

$25,900

 

Payne & Dolan, Inc.

Antioch, Illinois

$35,918.06

 

WHEREAS, the Public Works and Transportation Committee, the County Engineer and the Purchasing Agent have examined each bid, and it appears that the lowest responsible bidder is Peter Baker & Son Company, Lake Bluff, Illinois, their bid being $21,415.06, based on estimated quantities and unit prices; and

 

NOW, THEREFORE BE IT RESOLVED by this Lake County Board, that a contract be awarded to said Peter Baker & Son Company, Lake Bluff, Illinois, in accordance with their bid of $21,415.06 based on estimated quantities and unit prices, and that the Purchasing Agent, the County Clerk, and the County Engineer of Lake County be authorized and they are hereby directed to enter into a contract with said low bidder for  the HMA surface removal, patching and the addition of HMA leveling binder and surface courses on Magnolia Avenue in the Warren Township Road District, and designated as Section 17-14149-01-GM.

 

BE IT FURTHER RESOLVED that in as much as such estimated quantities are the best approximation that can be determined at this time, these quantities may be added to, deducted from, or modified from in the final determination of the contract cost in accordance with Chapter 605 of the Illinois Compiled Statutes, Act 5, Section 5-205.2 and Section 6-701.1 without further Board action.

 

BE IT FURTHER RESOLVED that this award be processed by the County Engineer for final approval of the Illinois Department of Transportation in accordance with the “Agreement of Understanding” between the Illinois Department of Transportation and Lake County, dated January 18, 2013, and subject to the approval of the Warren Township Road District Highway Commissioner.

 

DATED at Waukegan, Illinois, on April 11, 2017.