Lake County, IL
File #: 17-0145    Version: 1 Name: Multi-Department Storage Building
Type: resolution Status: Passed
File created: 1/30/2017 In control: Law & Judicial Committee
On agenda: Final action: 2/14/2017
Title: Joint resolution authorizing a contract with Stuckey Construction Company, Inc. of Waukegan, Illinois, for general contracting services required for construction of the Lake County Multi-Departmental Storage Facility in the amount of $3,139,000.
Attachments: 1. 16220 Award Recommendation, 2. 16220 Bid Tab

Title

Joint resolution authorizing a contract with Stuckey Construction Company, Inc. of Waukegan, Illinois, for general contracting services required for construction of the Lake County Multi-Departmental Storage Facility in the amount of $3,139,000.

 

Staff Summary

                     There is a need to construct a storage building on Lake County’s Libertyville Campus that can be utilized by a variety of different County departments.

                     This new 20,000 square feet (SF) facility has been designed for the Sheriff’s Office, Clerk of the Circuit Court, Environmental Health Services, Emergency Management, and Facility Operations.

                     Funding for the project was previously approved by the County Board through the Capital Improvement Program (CCIP) process, and the cost is within the 2017 budgeted amount.

                     An invitation to bid was issued and extended to 327 vendors and sealed bids were received from 11 general contractors ranging from $3,139,000 to $4,558,820.

                     Stuckey Construction Company, Inc. of Waukegan, Illinois, was determined to be the lowest responsive and responsible bidder who best meets the needs of the County in the amount of $3,139,000

 

Body

RESOLUTION

 

WHEREAS, there is a need to construct a communal storage building within Lake County’s Libertyville Campus that can be utilized by a variety of different County departments; and

 

WHEREAS, this new 20,000 SF facility has been designed for a variety of different County departments to utilize including the Sheriff’s Office, Clerk of the Circuit Court, Environmental Health Services, Emergency Management, and Facility Operations; and

 

WHEREAS, in accordance with Chapter 33.036 of the Lake County Purchasing Ordinance, a bid was called for by publication for General Contracting Services for the construction of the Lake County Multi-Departmental Storage Facility; and

 

WHEREAS, funding for the project was previously approved by the County Board through the CCIP process, this specific expense was expected and is included within the project’s overall budget; and

 

WHEREAS, sealed bids were received from eleven vendors at the Lake County Administrative Building, Waukegan, Illinois, on December 15, 2016, at 2:00 p.m.; and

 

WHEREAS, based on the criteria set forth in the bid; the staff evaluated all bids submitted and determined that the bid submitted by Stuckey Construction Company, Inc. of Waukegan, Illinois, in the amount of $3,139,000 is the lowest responsive and responsible bidder for Lake County; and

 

NOW, THEREFORE, BE IT RESOLVED, by this County Board of Lake County, Illinois, that Purchasing Agent is authorized to enter into a contract with Stuckey Construction Company, Inc. of Waukegan, Illinois, for general contracting services for construction of Lake County Multi-Departmental Storage Facility in the amount of $3,139,000 and charged to account # 101-1103180-82020.

 

DATED, at Waukegan, Lake County, Illinois, on February 14, 2017.