File #: 17-0026    Version: 1 Name: Cedar Lake Road, Illinois Route 120 to Nippersink Road; Phase II: Change Order No. 1 and Supplemental Appropriation
Type: resolution Status: Passed
File created: 1/3/2017 In control: Public Works and Transportation Committee
On agenda: Final action: 1/17/2017
Title: Joint resolution approving Change Order Number One consisting of an increase of $170,108.25, appropriating a supplemental amount of $70,000 of 1/4% Sales Tax for Transportation funds for Phase II design engineering services for the roadway reconstruction of Cedar Lake Road, from Illinois Route 120 to Nippersink Road, and designated as Section 08-00065-02-RS.
Title
Joint resolution approving Change Order Number One consisting of an increase of $170,108.25, appropriating a supplemental amount of $70,000 of 1/4% Sales Tax for Transportation funds for Phase II design engineering services for the roadway reconstruction of Cedar Lake Road, from Illinois Route 120 to Nippersink Road, and designated as Section 08-00065-02-RS.

Staff Summary
* Cedar Lake Road, Illinois Route 120 to Nippersink Road; Phase II: Change Order No. 1 and Supplemental Appropriation.
* Cedar Lake Road, from Illinois Route 120 to Nippersink Road, needs to be reconstructed and widened.
* Cedar Lake Road, from Illinois Route 120 to Nippersink Road, Phase II design engineering is under contract with Crawford, Murphy & Tilley, Inc., of Aurora, Illinois, in the amount of $543,160.20.
* Additional engineering services are needed, to the original scope of work, including additional coordination with the Lake County Forest Preserve, work related to the St. Joseph's Church site, south end path design/culvert modifications, and staging associated with the main culvert replacement.
* Change orders need to be approved by the standing committees for cumulative net increases over 10 percent.
* This Lake County Board, at its meeting of May 12, 2015, approved $655,000 of 1/4% Sales Tax for Transportation funds for these design engineering services.
* This resolution appropriates a supplemental amount of $70,000 of 1/4% Sales Tax for Transportation funds to cover Change Order Number One in the amount of $170,108.25.

Body
R E S O L U T I O N

WHEREAS, this Lake County Board, at its meeting of May 12, 2015, approved $655,000 of 1/4% Sales Tax for Transportation funds for Phase II design engineering services for the roadway reconstruction of Cedar Lake Road, from Illinois Route 120 to Nippersink Road; and

WHEREAS, the Phase II design engineering services for the roadway reconstruction of Cedar Lake Road, from Illinois Route 120 to Nippersink Road, is under contract...