File #: 16-0943    Version: 1 Name: Joint resolution authorizing execution of a contract with Joseph J. Henderson & Son, Inc. of Gurnee, IL in the amount of $862,000 for the Vernon Hills NCT WRF Phase 1 – 2016 Improvements Project.
Type: resolution Status: Passed
File created: 9/29/2016 In control: Public Works and Transportation Committee
On agenda: Final action: 10/11/2016
Title: Joint resolution authorizing a contract with Joseph J. Henderson & Son, Inc. of Gurnee, Illinois, in the amount of $862,000 for the construction of the Vernon Hills New Century Town (NCT) Water Reclamation Facility (WRF) Phase 1 - 2016 Improvements Project.
Attachments: 1. 16-0943 Vernon Hills NCT JJ Henderson Bid Tab

Title

Joint resolution authorizing a contract with Joseph J. Henderson & Son, Inc. of Gurnee, Illinois, in the amount of $862,000 for the construction of the Vernon Hills New Century Town (NCT) Water Reclamation Facility (WRF) Phase 1 - 2016 Improvements Project.

 

Staff Summary

                     The Vernon Hills NCT WRF is a major treatment plant that provides service to the Village of Vernon Hills and unincorporated portions of Southeast Central Lake County.

                     Repair or replacement of major equipment is necessary including the rehabilitation of 3 sludge presses, aeration piping improvements, gas detection equipment replacement and other miscellaneous repairs and improvements. 

                     An invitation to bid was extended to multiple contractors, eight bidders registered for the bid documents and responses were received from three contractors, ranging from $862,000 to $1,169,000.

                     Award of this contract is recommended to the lowest responsive, responsible bidder, Joseph J Henderson Inc., in the amount of $862,000.

 

Body

R E S O L U T I O N

 

WHEREAS, the Vernon Hills New Century Town (NCT) Water Reclamation Facility (WRF) is a major treatment plant that provides service to the Village of Vernon Hills and unincorporated portions of Southeast Central Lake County; and

 

WHEREAS, repair or replacement of major facility equipment is necessary including rehabilitation of 3 sludge presses, aeration piping improvements, gas detection equipment replacement along with other miscellaneous repairs and improvements; and

 

WHEREAS, in accordance with the Lake County Purchasing Ordinance, bids were called for by publication for the construction of the Vernon Hills NCT WRF Phase 1 - 2016 Improvements Project; and

 

WHEREAS, subsequent to said publication, invitations to bid were extended to multiple contractors; and

 

WHEREAS, three sealed bids were received and publicly opened in the office of the Public Works Department on Thursday, September 15, 2016, at 2:00 p.m.; and

 

WHEREAS, Joseph J. Henderson & Son, Inc. of Gurnee, Illinois, is the lowest responsive, responsible bidder in the amount of $862,000; two other bids were received ranging in amounts from $937,000 to $1,169,000.

 

NOW, THEREFORE, BE IT RESOLVED, by this County Board of Lake County, Illinois, that the Purchasing Agent is hereby authorized and directed to execute a contract with Joseph J. Henderson & Son, Inc. of Gurnee, Illinois, in the amount of $862,000 for the construction of Vernon Hills NCT WRF Phase 1 - 2016 Project and charging the costs thereof to various accounts.

 