Title
Joint committee action item approving Change Order No. 1 consisting of an increase of $39,652.19 for additions to the Warren Township Resurfacing Contract, and designated as Section 16-14149-01-GM.
Staff Summary
• Warren Township Motor Fuel Tax Resurfacing Project: Change Order No. 1.
• Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• Warren Township project is under contract with Peter Baker & Son Co. in the amount of $91,000.29.
• Warren Township added an additional 986 feet of curb replacement to the project, adding additional cost to the contract.
• 100 percent of the additional cost was paid by Warren Township from their general fund.
Body
Summary:
Original awarded contract: $91,000.29
Change Order No. 1: $39,652.19
Sum of all changes: $39,652.19