Lake County, IL
File #: 16-0917    Version: 1 Name: Warren Township Motor Fuel Tax Resurfacing Project: Change Order No. 1
Type: committee action item Status: Passed
File created: 9/27/2016 In control: Public Works and Transportation Committee
On agenda: Final action: 10/5/2016
Title: Joint committee action item approving Change Order No. 1 consisting of an increase of $39,652.19 for additions to the Warren Township Resurfacing Contract, and designated as Section 16-14149-01-GM.
Attachments: 1. 16-0917 Warren Township Change Order 1.pdf

Title

Joint committee action item approving Change Order No. 1 consisting of an increase of $39,652.19 for additions to the Warren Township Resurfacing Contract, and designated as Section 16-14149-01-GM.

 

Staff Summary

                     Warren Township Motor Fuel Tax Resurfacing Project:  Change Order No. 1.

                     Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.

                     Warren Township project is under contract with Peter Baker & Son Co. in the amount of $91,000.29.

                     Warren Township added an additional 986 feet of curb replacement to the project, adding additional cost to the contract.

                     100 percent of the additional cost was paid by Warren Township from their general fund.

 

Body

 

Summary:

 

Original awarded contract:                     $91,000.29

Change Order No. 1:                                          $39,652.19

 

Sum of all changes:                                          $39,652.19