Lake County, IL
File #: 16-0818    Version: 1 Name: Buffalo Grove Road Patching: Change Order No. 2
Type: committee action item Status: Passed
File created: 8/23/2016 In control: Public Works and Transportation Committee
On agenda: Final action: 9/7/2016
Title: Joint committee action item approving change order number two consisting of an increase of $84,314.34 for additions to the Buffalo Grove Road patching construction contract, and designated as Section 16-00249-04-RS.
Attachments: 1. 16-0818 Buffalo Grove Road Patching Change Order No 2.pdf

Title

Joint committee action item approving change order number two consisting of an increase of $84,314.34 for additions to the Buffalo Grove Road patching construction contract, and designated as Section 16-00249-04-RS.

 

Staff Summary

                     Buffalo Grove Road Patching: Change Order Number Two.

                     Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.

                     Buffalo Grove Road patching project is under contract with J.A. Johnson Paving Co. in the amount of $306,425.23.

                     The significant items driving this change order are the balancing of construction items, and field adjustments made to fulfill the intent of the contract.

 

Body

 

Summary:

                                          Original awarded contract:                                                                                    $306,425.23

                                          Change order number two:                                                                                    $84,314.34

                                          Previously approved change order:                     $14,527.05

                                          Sum of all changes:                                                                                                                              $98,841.39