Lake County, IL
File #: 16-0745    Version: 1 Name: Illinois Route 120, Traffic Signal Interconnect: IDOT Agreement and Appropriation
Type: resolution Status: Passed
File created: 7/27/2016 In control: Public Works and Transportation Committee
On agenda: Final action: 8/9/2016
Title: Joint resolution authorizing an agreement with the State of Illinois, by and through the Illinois Department of Transportation (IDOT), for the modernization and interconnection of the traffic signals along Illinois Route 120, from Illinois Route 134 to U.S. Route 45, and for the widening, resurfacing and channelization at the intersection of Illinois Route 120 and Hainesville Road, appropriating $45,000 of 1/4% Sales Tax for Transportation funds, and designated as Section 12-00999-27-TL and State Job Number C-91-401-13.
Attachments: 1. 16-0745 ITS PASSAGE IL RTE 120 IDOT Agreement Draft.pdf

Title

Joint resolution authorizing an agreement with the State of Illinois, by and through the Illinois Department of Transportation (IDOT), for the modernization and interconnection of the traffic signals along Illinois Route 120, from Illinois Route 134 to U.S. Route 45, and for the widening, resurfacing and channelization at the intersection of Illinois Route 120 and Hainesville Road, appropriating $45,000 of ¼% Sales Tax for Transportation funds, and designated as Section 12-00999-27-TL and State Job Number C-91-401-13.

 

Staff Summary

                     Illinois Route 120, Traffic Signal Interconnect: IDOT Agreement and Appropriation.

                     The traffic signals along Illinois Route 120, from Illinois Route 134 to U.S. Route 45, will be modernized and connected to Lake County PASSAGE.

                     This work is part of a larger IDOT improvement project that will widen, resurface and provide channelization at the intersection of Illinois Route 120 and Hainesville Road.

                     This resolution authorizes the execution of an agreement with the State of Illinois and appropriates $45,000 of ¼% Sales Tax for Transportation funds for the County’s share of this project.

 

Body

R E S O L U T I O N

 

WHEREAS, Lake County PASSAGE is a cooperative initiative of the Illinois Department of Transportation (IDOT) and Lake County to implement an Intelligent Transportation System (ITS) in Lake County; and

 

WHEREAS, Lake County and the State of Illinois believe it would be beneficial to the safety and welfare of the motoring public if traffic signals situated along Illinois Route 120, from Illinois Route 134 to U.S. Route 45, could be modernized and interconnected with Lake County PASSAGE and the intersection of Illinois Route 120 at Hainesville Road could be widened, resurfaced and channelized; and

 

WHEREAS, the State of Illinois and Lake County are desirous of entering into an agreement for the County’s share of the above proposed improvement, a draft copy of which is attached hereto; and

 

WHEREAS, an appropriation of funds is required.

 

NOW, THEREFORE BE IT RESOLVED by this Lake County Board, that the County Board Chair, the County Clerk and the County Engineer of Lake County are authorized, and they are directed to execute on behalf of Lake County, an agreement, and any subsequent amendments thereto, pertaining to the financing of the above named improvement.

 

BE IT FURTHER RESOLVED that the County Engineer shall transmit, in writing, the final agreement and any amendments to be executed by the County Board Chair and the County Clerk.  

 

BE IT FURTHER RESOLVED that there is appropriated $45,000 of ¼% Sales Tax funds for Transportation funds for the County’s share of this improvement, and designated as Section 12-00999-27-TL and State Job Number C-91-401-13.

 

BE IT FURTHER RESOLVED that a copy of this agreement, when executed in its final form, be submitted to IDOT for their approval and final processing.

 

DATED at Waukegan, Illinois, on August 9, 2016.