Lake County, IL
File #: 16-0592    Version: 1 Name: Joint resolution executing a contract with RJ Underground, Inc. of Kenosha, Wisconsin for the Arden Shores Water Main Replacement Project in the amount of $594,204.
Type: resolution Status: Passed
File created: 6/2/2016 In control: Public Works and Transportation Committee
On agenda: Final action: 6/14/2016
Title: Joint resolution executing a contract with RJ Underground, Inc., Kenosha, Wisconsin, for the Arden Shores Water Main Replacement Project in the amount of $594,204.
Attachments: 1. 16-0592 Arden Shores Water Main Bid Tab.pdf

Title

Joint resolution executing a contract with RJ Underground, Inc., Kenosha, Wisconsin, for the Arden Shores Water Main Replacement Project in the amount of $594,204.

 

Staff Summary

                     The Arden Shores water system was originally constructed over sixty years ago and must be upgraded to comply with current standards to insure public health and safety.

                     The Arden Shores Water Main Project focuses on the replacement of the water main along Bay Shore Drive, Hillside Avenue, Glendell Avenue and Juneway Terrace.

                     This improvement will enable Lake County to purchase Lake Michigan water on a wholesale basis from the City of North Chicago for distribution to residents in the Arden Shores Estates Subdivision.

                     An invitation to bid was extended to 16 vendors and responses were received from four contractors, ranging from $594,204 and $648,734.

                     RJ Underground, Inc. submitted the lowest responsive and responsible bid in the amount of $594,204. 

 

Body

R E S O L U T I O N

 

WHEREAS, the County of Lake owns and operates water supply systems that serve various communities throughout the County; and

                     

WHEREAS, the water main distribution system in Arden Shores Estates Subdivision was originally constructed over 60 years ago and requires replacement to meet current IEPA standards; and

                               

WHEREAS, in accordance with the Lake County Purchasing Ordinance, bids were called for by publication for the Arden Shores Water Main Replacement Project; and

 

WHEREAS, subsequent to said publication, invitations to bid were extended to 16 contractors; and

 

WHEREAS, four sealed bids were received and publicly opened in the office of the Public Works Department on Thursday, May 26, 2016, at 2:00 p.m.; and

 

WHEREAS, four bids were received ranging from $594,204 to $648,734 with RJ Underground, Inc., being the lowest responsive and responsible bidder in the amount of $594,204.

 

NOW, THEREFORE, BE IT RESOLVED, by this County Board of Lake County, Illinois, that the Purchasing Agent is hereby authorized and directed to execute a contract with RJ Underground, Inc., Kenosha, Wisconsin, in the amount of $594,204 for the Arden Shores Estates Water Main Replacement Project and charging the costs thereof to account number 610-4816398.

 

DATED at Waukegan, Lake County, Illinois on this 14th day of June, A.D., 2016.