Joint committee action item approving Change Order No. 2 consisting of an increase of $1,662.50 for additions to the Various Culvert Linings Construction Contract, and designated as Section No. 14-00999-06-DR.
Staff Summary
• 2015 Culvert Replacement: LCDOT Change Order No. 2.
• Change orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• The 2015 Culvert Replacement project is under contract with Hoerr Construction, Inc., in the amount of $152,530.
• The additional funds are necessary as the culvert lengths were determined to be slightly longer in the field than were estimated.
• Previously approved change order added a culvert lining under Cedar Lake Road.
Body
SUMMARY
Original awarded contract: $152,530
Change Order No.: 2: $1,662.50
Previously approved change order: $15,170
Sum of all changes: $16,832.50