Title: Joint committee action item approving Change Order No. 2 consisting of an increase of $1,662.50 for additions to the Various Culvert Linings Construction Contract, and designated as Section No. 14-00999-06-DR.
Attachments: 1. 16-0573 2015 Culvert Replacement Change Order No 2 .pdf

Title

Joint committee action item approving Change Order No. 2 consisting of an increase of $1,662.50 for additions to the Various Culvert Linings Construction Contract, and designated as Section No. 14-00999-06-DR.

 

Staff Summary

                     2015 Culvert Replacement: LCDOT Change Order No. 2.

                     Change orders need to be approved by the standing committees for cumulative net increases over 10 percent.

                     The 2015 Culvert Replacement project is under contract with Hoerr Construction, Inc., in the amount of $152,530.

                     The additional funds are necessary as the culvert lengths were determined to be slightly longer in the field than were estimated.

                     Previously approved change order added a culvert lining under Cedar Lake Road.

 

Body

SUMMARY

 

                     Original awarded contract:                                                                  $152,530

                     Change Order No.: 2:                                                                                                            $1,662.50

                     Previously approved change order:                        $15,170

                     Sum of all changes:                                                                                                            $16,832.50