Lake County, IL
File #: 12-0527    Version: 1 Name: Construction of Addition to Building C at the Division of Transportation: Contract Award and Supplemental Appropriation
Type: resolution Status: Passed
File created: 4/24/2012 In control: Public Works and Transportation Committee
On agenda: Final action: 5/8/2012
Title: Joint resolution awarding a contract for the construction of an addition to Building C at the Division of Transportation highway garage in Libertyville to the lowest responsible bidder, Camosy Incorporated, Zion, Illinois, in the amount of $988,000, providing a supplemental appropriation of $230,000 of Motor Fuel Tax funds and designated as Section 11-00214-19-MG.
Attachments: 1. Bid Tab - Building C Addition

Title
Joint resolution awarding a contract for the construction of an addition to Building C at the Division of Transportation highway garage in Libertyville to the lowest responsible bidder, Camosy Incorporated, Zion, Illinois, in the amount of $988,000, providing a supplemental appropriation of $230,000 of Motor Fuel Tax funds and designated as Section 11-00214-19-MG.

Staff Summary
· Construction of Addition to Building C at the Division of Transportation: Contract Award and Supplemental Appropriation.
· The construction of an addition to Building C will replace three obsolete buildings used to house the emergency detour trailer, the portable changeable message signs, the carpentry shop, and the road maintenance materials.
· A total of four bids were received, ranging from $988,000 to $1,025,000, and the lowest responsible bidder is Camosy Incorporated, Zion, Illinois, in the amount of $988,000.
· This resolution authorizes execution of the contract and provides for a supplemental appropriation of $230,000 of Motor Fuel Tax funds.

Body
R E S O L U T I O N

WHEREAS, pursuant to authority granted by this Lake County Board, the County Engineer heretofore called for sealed bids, by publication, for the construction of an addition to Building C, at the Division of Transportation highway garage in Libertyville, and designated as Section 11-00214-19-MG; and

WHEREAS, pursuant to said publication and calling for said bids, sealed bids were received and opened on April 17, 2012, at 10:00 a.m. at the Lake County Division of Transportation in Libertyville, Illinois, a tabulation of said bids being as follows:

Camosy Incorporated
Zion, IL
$988,000

Tri-state Enterprises, Inc.
Romeoville, IL
$1,021,786

Boller Construction
Waukegan, IL
$1,023,000

Joseph J. Henderson & Son, Inc.
Gurnee, IL
$1,025,000

WHEREAS, the Public Works and Transportation Committee, the County Engineer and the Purchasing Agent have examined each bid, and it appears that the lowest re...