Title
Joint committee action item approving Change Order No. 3 consisting of an increase of $16,666.12 for additional design engineering services to the Hunt Club Road Roundabouts at Millburn Rd and at Wadsworth Rd, designated as Section No. 02-00076-13-CH.
Staff Summary
· Hunt Club Road Roundabouts at Millburn Road and Wadsworth Road, Design Engineering Services: LCDOT Change Order No. 3
· Change Orders need to be approved by the standing committees for cumulative net increases over 10%.
· The design of the Hunt Club Road Roundabouts project is under contract with Strand and Associates, in the amount of $330,207.88.
· Additional design engineering services are being requested for right-of-way and plan sheet changes for the acquisition of permanent easements.
· Summary: Original awarded contract - $266,302.23; Change Order No 3 - $16,666.12; Sum of all changes - $80,571.77