File #: 10-1330    Version: 1 Name: 2010 Concrete Patching: LCDOT Change Order No. 2 & Final
Type: committee action item Status: Passed
File created: 12/21/2010 In control: Public Works and Transportation Committee
On agenda: Final action: 1/5/2011
Title: Joint committee action item approving Change Order No. 2 & final consisting of a net decrease of $4,630.38 to the cumulative previous change orders to the 2010 Concrete Patching, designated as Section No. 10-00000-14-GM.
Attachments: 1. 10-1330 2010 Concrete Patching Change Order No 2 and Final.pdf
Title
Joint committee action item approving Change Order No. 2 & final consisting of a net decrease of $4,630.38 to the cumulative previous change orders to the 2010 Concrete Patching, designated as Section No. 10-00000-14-GM.
Staff Summary
·      2010 Concrete Patching:  LCDOT Change Order No. 2 & final
·      Change Orders need to be approved by the standing committees for cumulative net increases over 10%.
·      The 2010 Concrete Patching is under contract, at unit prices, with Acura, Inc. in the amount of $53,837.00.
·      Previous Change Order No. 1, as approved, was for additional work, and this Change Order No. 2 and final is the balancing change order for actual work completed at awarded unit prices.
·      The balancing change order is a net decrease of $4,630.38 from the cumulative amount of Change Order No. 1.
·      Summary: Original awarded contract - $53,837.00; Change Order No. 2 & final -($4,630.38); Sum of all changes - $10,139.62