Title
Joint committee action item approving Change Order No.1 consisting of an increase of $13,817 for additions to the Hainesville Road Bike Path (Stage IIb), Design Engineering Services, designated as Section No. 08-00072-11-BT.
Staff Summary
· Hainesville Road Bike Path (Stage IIb), Design Engineering Services: LCDOT Change Order No. 1
· Change Orders need to be approved by the standing committees for cumulative net increases over 10%.
· The design of the Hainesville Road Bike Path (Stage IIb), from IL Rte. 120 to 175 ft. south of Heritage Trail, is under contract with Hampton, Lenzini and Renwick, Inc., in the amount of $64,527.
· A change order is required to revise plans to avoid the need for a permanent easement from a private property owner.
· Summary: Original awarded contract - $64,527; Change Order No.1 - $13,817; Sum of all changes - $13,817.