File #: 17-0807    Version: 1 Name: Rollins Road Drainage Improvement: Contract Award
Type: resolution Status: Passed
File created: 7/24/2017 In control: Public Works and Transportation Committee
On agenda: Final action: 8/8/2017
Title: Joint resolution authorizing a contract with Copenhaver Construction, Gilberts, Illinois, in the amount of $297,159.36 for the Rollins Road at Wilson Boulevard drainage improvement, and designated as Section 15-00080-60-DR.
Attachments: 1. Bid Tab, Rollins Road Drainage Improvements.pdf
Title
Joint resolution authorizing a contract with Copenhaver Construction, Gilberts, Illinois, in the amount of $297,159.36 for the Rollins Road at Wilson Boulevard drainage improvement, and designated as Section 15-00080-60-DR.

Staff Summary
* Rollins Road Drainage Improvement: Contract Award.
* Rollins Road at Wilson Boulevard will be improved with increased drainage capacity, including storm sewer, grading, patching, utility relocations and site restoration.
* A total of five bids were received, ranging from $297,159.36 to $399,703.70, and the lowest responsible bidder is Copenhaver Construction, Gilberts, Illinois, in the amount of $297,159.36.
* This project is included in the highway improvement program.

Body
R E S O L U T I O N

WHEREAS, pursuant to authority granted by this Lake County Board, the Acting County Engineer heretofore called for sealed bids, by publication, for the Rollins Road at Wilson Boulevard drainage improvement, and designated as Section 15-00080-60-DR.

WHEREAS, pursuant to said publication calling for said bid, sealed bids were received and opened on July 18, 2017, at 10:00 a.m. at the Lake County Division of Transportation in Libertyville, Illinois; a tabulation of said bids being as follows:

Copenhaver Construction
Gilberts, Illinois
$297,159.36

Maneval Construction
Ingleside, Illinois
$321,780.70

Campanella & Sons, Inc.
Wadsworth, Illinois
$334,600.40

Berger Excavating Contractors
Wauconda, Illinois
$336,659.70

A Lamp Concrete Contractors, Inc.
Schaumburg, Illinois
$399,703.70

WHEREAS, the Public Works and Transportation Committee, the Acting County Engineer and the Purchasing Agent have examined each bid, and it appears that the lowest responsible bidder is Copenhaver Construction, Gilberts, Illinois, their bid being $297,159.36 based on estimated quantities and unit prices; and

WHEREAS, this Lake County Board, by prior resolution at its meeting of May 9, 2017, appropriated $440,000 of County Bridge Tax funds for the...

Click here for full text