Lake County, IL
File #: 10-0135    Version: 1 Name: Arlington Heights Road Northbound over Buffalo Creek, Bridge Deck Beam Replacements; Supplemental Phase I: IDOT Agreement.
Type: resolution Status: Passed
File created: 1/28/2010 In control: Public Works and Transportation Committee
On agenda: Final action: 2/9/2010
Title: Joint resolution authorizing the execution of Amendment #1 to the Phase I agreement for the use of federal highway funds between the State of Illinois and Lake County for the provision of additional Phase I preliminary engineering services for the proposed replacement of the deck beams of the bridge carrying northbound Arlington Heights Road over Buffalo Creek and designated as Section 05-00193-04-BR.
Attachments: 1. Arlington Heights Road Northbound over Buffalo Creek, Bridge Deck
Title
Joint resolution authorizing the execution of Amendment #1 to the Phase I agreement for the use of federal highway funds between the State of Illinois and Lake County for the provision of additional Phase I preliminary engineering services for the proposed replacement of the deck beams of the bridge carrying northbound Arlington Heights Road over Buffalo Creek and designated as Section 05-00193-04-BR.

Staff Summary
· Arlington Heights Rd Northbound over Buffalo Creek, Bridge Deck
Beam Replacements; Supplemental Phase I: IDOT Agreement.
· The county has been allocated Federal Highway Bridge Program (HBP) funds to repair this bridge and IDOT administers all federal funds.
· Phase I preliminary engineering is being expanded to include a bridge scour analysis and an asbestos verification and associated reporting.
· This Amendment #1 to the Phase 1 agreement provides for the county to receive 80% reimbursement for the additional cost of Phase I.

Body
R E S O L U T I O N

WHEREAS, Arlington Heights Road (County Highway 79) is a designated route on the county highway system; and

WHEREAS, the bridge deck beams of the bridge carrying northbound Arlington Heights Road over Buffalo Creek are at the end of their useful service life; and

WHEREAS, the State of Illinois and Lake County believe it would be beneficial to the safety and welfare of the motoring public if said bridge deck beams could be replaced; and

WHEREAS, Phase I studies are required to utilize federal highway funds for the above-proposed improvements; and

WHEREAS, the County Board of Lake County, Illinois at its meeting of August 12, 2008 authorized the execution of an agreement for these federal highway funds between the State of Illinois and Lake County for federal reimbursement of 80% of the Phase I engineering services (Preliminary Engineering) for said improvement; and

WHEREAS, this County Board of Lake County, Illinois at its meeting of August 12, 2008, appropriated $45,000 o...

Click here for full text