Joint committee action item approving Change Order Number Three consisting of an increase of $10,372.70 for additions to the Cedar Lake Road 2022 Culvert Replacements construction contract.
Staff Summary
• Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• The Cedar Lake Road 2022 Culvert Replacement project is under contract with Copenhaver Construction, Inc., Gilberts, Illinois, in the amount of $372,644 as approved by the County Board on August 9, 2022 and designated as Section 20-00153-12-DR.
• The sum of all contract change orders to date is $38,380.01, which represents a 10.3% increase over the original awarded contract amount.
Body
JOINT COMMITTEE ACTION ITEM
Summary:
Original awarded contract: $372,644
Change Order Number Three: $ 10,372.70
Previously Approved Change Order Number Two: $ 13,393.16
Previously Approved Change Order Number One: $ 14,614.15
Sum of all Change Orders: $ 38,380.01
Total revised contract amount (including all change orders): $411,024.01
Original contract appropriation amount: $490,000