Legislation Details

File #: 20-0704    Version: 1 Name: IL Route 120, Knight Avenue to IL 131: Phase II Consultant Change Order Number 3
Type: committee action item Status: Passed
File created: 5/20/2020 In control: Public Works, Planning & Transportation Committee
On agenda: Final action: 6/4/2020
Title: Joint committee action item approving Change Order Number Three consisting of an increase of $21,883 to the Phase II engineering consultant agreement for the widening and resurfacing of Illinois Route 120, from Knight Avenue to Illinois Route 131.
Attachments: 1. 20-0704 IL Rte 120 Change Order 3 Supplement, 2. 20-0704 Location Map, IL Route 120 (Knight Ave to IL Route 131), 3. 20-0704 Vendor Disclosure, Patrick Engineering

Title

Joint committee action item approving Change Order Number Three consisting of an increase of $21,883 to the Phase II engineering consultant agreement for the widening and resurfacing of Illinois Route 120, from Knight Avenue to Illinois Route 131.

 

Staff Summary

•                     Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.

•                     Illinois Route 120 (Knight Avenue to Illinois Route 131) widening and resurfacing project is under contract with Patrick Engineering Inc., Lisle, Illinois, in the amount of $319,389.96 as approved by the County Board on November 11, 2015, and designated as Section 12-00999-31-WR.

•                     Additional engineering services are necessary for several revisions to the original scope of work as detailed in the attached Supplement Number Three.

•                     Change Order Number Three includes revisions to the plans required as a result of coordination with the Illinois Department of Transportation (IDOT) to accommodate their upcoming projects in the area as well as new IDOT permit plan requirements.

•                     Change Order Number Two corrected an accounting error in the original contract document.

•                     Change Order Number One included work to cover plan and plat revisions that resulted from ROW negotiations with adjacent property owner.

 

Body

COMMITTEE ACTION ITEM

 

Summary:

 

Original awarded contract:                     $ 319,389.96

 

Change Order Number One:                     $   23,865

Change Order Number Two:                     $     5,000

Change Order Number Three:                     $   21,883

Sum of all Change Orders:                     $   50,748

 

Total revised contract amount (including all change orders): $ 370,137.96

 

Original contract appropriation amount:  $ 385,000.