Joint committee action approving Change Order No. 4 for construction contract changes related to the Deerfield Road Forcemain Relocation Project.
Staff Summary
· Change orders that exceed 10% of the original contract amount must be reviewed and approved by the Public Works and Transportation and Finance and Administrative Committtees. The following change orders associated with the Deerfield Road Forcemain Relocation Project total $24,020.60 and exceeded 10% of the contract.
o Change Orders No. 1, 2 and 3 were previously approved in the amount of $22,320.60.
o Change Order No. 4 is in the amount of $1,700 to provide for additional asphalt repair to Deerfield Road on the west side of the Des Plaines River.