Title
Joint committee action item approving Change Order Number Seven in the amount of $6,712.75 for additions to the Hutchins Road Bridge construction contract.
Staff Summary
• Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• The sum of all change orders is $153,385.35, which represents a 10.45 percent cumulative increase over the original awarded contract.
• Hutchins Road Bridge is under contract with Lorig Construction Company in the amount of $1,467,849.51 as approved by the County Board on April 9, 2019, and designated as Section 17-00275-02-BR.
• The contract included removing the existing triple cell pipe culvert, replacing with a single span bridge, in-stream work, pavement removal, full depth hot-mix asphalt paving, curb and gutter, drainage, erosion control, and site restoration.
Body
COMMITTEE ACTION ITEM
Summary:
Original awarded contract: $1,467,849.51
Change Order Number One: $5,700
Change Order Number Two: $23,011.58
Change Order Number Three: $34,493.85
Change Order Number Four: $65,790.10
Change Order Number Five: -$21,319.79
Change Order Number Six: $38,996.86
Change Order Number Seven: $6,712.75
Sum of all Change Orders: $153,385.35
Total revised contract amount (including all change orders): $1,621,234.86.
Original contract appropriation amount: $1,761,500.