Title
Joint committee action item approving Change Order No.1, consisting of an increase of $24,313.72 for additions to the Lake Villa Township 2014 Motor Fuel Tax (MFT) project, and designated as Section No.14-09101-01-GM.
Staff Summary
· Lake Villa Township 2014 MFT: Change Order No. 1.
· Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
· The Lake Villa Township 2014 MFT project is under contract with Peter Baker & Son, Co. in the amount of $202,424.21.
· Balancing of construction items are being requested for an addition to the original scope of work as detailed in the attached Change Order No.1; major items contributing to the cost are additions to Hot Mix Asphalt Surface Course.
Body
Summary:
Original awarded contract: $202,424.21
Change Order No.1: $24,313.72
Sum of all changes: $24,313.72