Lake County, IL
File #: 19-0546    Version: 1 Name: Joint committee action ratifying Change Orders # 1 - 3 for the Supervisory Control And Data Acquisition (SCADA) Phase II contract with Wunderlich-Malec Services, Inc. of Minnetonka, MN resulting in a net cost reduction of $227,150.00 from $1,146,751 to $9
Type: committee action item Status: Joint Committee
File created: 3/25/2019 In control: Public Works, Planning & Transportation Committee
On agenda: Final action: 4/4/2019
Title: Joint committee action ratifying Change Order Numbers One through Three for the Supervisory Control and Data Acquisition (SCADA) Phase II contract with Wunderlich-Malec Services, Inc., Minnetonka, Minnesota, resulting in a net cost reduction of $227,150 from $1,146,751 to $919,601.
Attachments: 1. 19-0546 SCADA Wunderlich Contract 2014.10.08.pdf
Title
Joint committee action ratifying Change Order Numbers One through Three for the Supervisory Control and Data Acquisition (SCADA) Phase II contract with Wunderlich-Malec Services, Inc., Minnetonka, Minnesota, resulting in a net cost reduction of $227,150 from $1,146,751 to $919,601.

Staff Summary
* On January 27, 2015, a contract was issued to Wunderlich-Malec Services, Inc. for the construction and implementation of a SCADA system to communicate and collect data from remote Public Works sites to control centers at the water reclamation facilities.
* Change Order Number One removed several sites from the project, converted some sites from radio transmission to cellular communication and removed construction of a 190-foot communication tower resulting in a decreased cost of $322,085.
* Change Order Number Two added installation of a radio antenna at East Main Pump Station, converted additional radio sites to cellular communication and resolved data transfer problems at the Washington Street Storm Station resulting in an increased cost of $620.
* Change Order Number Three addressed additional time and materials to resolve data transfer problems to the Mill Creek water reclamation facility and the purchase of additional SCADA tag software licenses resulting in an additional cost of $94,330.
* In accordance with Article 8, Section 101(2) of the Lake County Purchasing Ordinance, these change orders were not reasonably foreseeable at the time the contract was signed.
* This resolution authorizes and directs the County Purchasing Agent to execute a contract change order with Wunderlich-Malec Services, Inc., reducing the original contract value by $227,150, from $1,146,751 to $919,601.

Body
R E S O L U T I O N

WHEREAS, Lake County owns, operates and maintains over 150 water and wastewater facilities throughout the County, which require differing levels of automated control and data acquisition; and

WHEREAS, the County has developed a master plan for Superviso...