Title: Joint committee action item approving Change Order Number Two, consisting of an increase of $11,536.68, for the Phase II design engineering services to stabilize an existing sheet piling wall adjacent to the multi-use path on the north side of Grass Lake Road, and designated as Section 16-00059-11-BR.
Attachments: 1. 18-0020 Grass Lake Road 2018 Retaining Wall Maintenance Change Order Number Two, 2. 18-0020 Grass Lake Road 2018 Retaining Wall Maintenance Change Order Number Two Consultant

Title

Joint committee action item approving Change Order Number Two, consisting of an increase of $11,536.68, for the Phase II design engineering services to stabilize an existing sheet piling wall adjacent to the multi-use path on the north side of Grass Lake Road, and designated as Section 16-00059-11-BR.

 

Staff Summary

                     Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.

                     The 2018 Grass Lake Road retaining wall maintenance project is under contract with Amec Foster Wheeler Environment and Infrastructure, Inc. in the amount of $77,844.

                     Change Order Number One included additional structural and roadway work added to the scope of services, increasing the cost by $16,732.10.

                     Change Order Number Two is related to a change in the design scope from two stages of construction to four stages of construction.  The design change will reduce traffic delays at the temporary traffic signals during construction, and increases the design cost by $11,536.68, bringing the total of all change orders to $28,268.78. 

 

Body

Committee Action Item

Summary:

 

                                          Original awarded contract:                                                               $77,844

 

 

                                          Change Order Number Two:                                          $11,536.68

                                          Change Order Number One:                                          $16,732.10

                                          Sum of all changes:                                                                                    $28,268.78