Joint committee action item approving Change Order Number Two, consisting of an increase of $11,536.68, for the Phase II design engineering services to stabilize an existing sheet piling wall adjacent to the multi-use path on the north side of Grass Lake Road, and designated as Section 16-00059-11-BR.
Staff Summary
• Change Orders need to be approved by the standing committees for cumulative net increases over 10 percent.
• The 2018 Grass Lake Road retaining wall maintenance project is under contract with Amec Foster Wheeler Environment and Infrastructure, Inc. in the amount of $77,844.
• Change Order Number One included additional structural and roadway work added to the scope of services, increasing the cost by $16,732.10.
• Change Order Number Two is related to a change in the design scope from two stages of construction to four stages of construction. The design change will reduce traffic delays at the temporary traffic signals during construction, and increases the design cost by $11,536.68, bringing the total of all change orders to $28,268.78.
Body
Committee Action Item
Summary:
Original awarded contract: $77,844
Change Order Number Two: $11,536.68
Change Order Number One: $16,732.10
Sum of all changes: $28,268.78