Lake County, IL
File #: 09-2127    Version: 1 Name: Washington Street, Additional Stormwater Detention Capacity: City of Waukegan Agreement and Appropriation.
Type: resolution Status: Passed
File created: 10/26/2009 In control: Public Works and Transportation Committee
On agenda: Final action: 11/10/2009
Title: Joint resolution authorizing the execution of an agreement between Lake County and the City of Waukegan for the construction of additional stormwater detention capacity along Washington Street west of Noll Street in the City of Waukegan. This resolution also appropriates $25,000 of County Bridge Tax funds for this improvement designated as Section 09-00220-06-DR.
Attachments: 1. Washington St Stormwater_20091026125246.pdf
Title
Joint resolution authorizing the execution of an agreement between Lake County and the City of Waukegan for the construction of additional stormwater detention capacity along Washington Street west of Noll Street in the City of Waukegan. This resolution also appropriates $25,000 of County Bridge Tax funds for this improvement designated as Section 09-00220-06-DR.

Staff Summary
· Washington Street, Additional Stormwater Detention Capacity: City of Waukegan Agreement and Appropriation.
· The City of Waukegan is the lead agency for the Washington Street flood reduction project located north of Washington Street near Noll Street.
· The addition of detention basins north of Washington Street was a recommendation of an SMC study.
· The LCDOT would benefit from the reduced occurrences of flooding overtopping Washington Street.
· This resolution authorizes the execution of an agreement with the City of Waukegan and appropriates $25,000 of County Bridge Tax funds as the County’s total contribution.

Body
R E S O L U T I O N

WHEREAS, Washington Street (County Highway 45) is a designated route on the county highway system; and

WHEREAS, the section of Washington Street between Green Bay Road and Teske Boulevard experiences periodic overtopping of the roadway; and

WHEREAS, the results of a Lake County Stormwater Management Commission study calls for additional upstream stormwater detention capacity to be constructed; and

WHEREAS, Lake County and the City of Waukegan are desirous of entering into an agreement for the construction of the above-said additional upstream stormwater detention capacity, a draft copy of which is attached hereto.

NOW, THEREFORE BE IT RESOLVED, by this County Board of Lake County, Illinois, that the Chair of the County Board, the County Clerk and the County Engineer of Lake County are authorized and they are directed to execute an agreement pertaining to the financing of the above-named improvement. The County Engineer shall trans...

Click here for full text