Joint resolution authorizing a contract for the modifications of older existing stormwater detention basins to improve functionality and water quality to Campanella & Sons, Inc., Wadsworth, Illinois, in the amount of $215,938.27, providing a supplemental appropriation of $70,000 of Matching Tax funds, and designated as Section 11-00999-24-DR.
Staff Summary
· 2012 Stormwater Detention Basin Retrofits: Contract Award and Supplemental Appropriation.
· Lake County Division of Transportation proposes to convert certain dry detention basins to wet detention basis to improve stormwater management and water quality treatment.
· A total of six bids were received, ranging from $215,938.27 to $300,957.45, and the lowest responsible bidder is Campanella & Sons, Inc., Wadsworth, Illinois, in the amount of $215,938.27
· This resolution authorizes execution of the contract, and provides for a supplemental appropriation of $70,000 of Matching Tax funds.
Body
R E S O L U T I O N
WHEREAS, pursuant to authority granted by this Lake County Board, the County Engineer heretofore called for sealed bids, by publication, for the 2012 Stormwater Detention Basin Retrofits, and designated as Section 11-00999-24-DR; and
WHEREAS, pursuant to said publication calling for said bids, sealed bids were received and opened on December 18, 2012, at 10:00 AM at the Lake County Division of Transportation in Libertyville, Illinois; a tabulation of said bids being as follows:
Campanella & Sons, Inc.
Wadsworth, IL
$215,938.27
Maneval Construction Co., Inc.
Grayslake, IL
$225,026.19
Berger Excavating Contractors
Wauconda, IL
$227,079.25
Sheridan Plumbing and Sewer, Inc.
Bedford Park, IL
$252,880.50
Copenhaver Construction
Gilberts, IL
$277,685.75
Landmark Contractors, Inc.
Huntley, IL
$300,957.45
WHEREAS, the Public Works and Transportation Committee, the County Engineer and the Purchasing Agent have examined each bid, and it appears that the lowest responsible bidder is Campanella &...